Ask the Scholar
Document scope · 1 page
Scholar
Ask about this object, its catalog metadata, its source description, or the page inventory.
For page-specific OCR and visual context, open one of the page chats.
Scholar Source Context
Document identity
localId
118569128
label
[General Correspondence - Cicconi, Jim - 1983] [C-D]
core
doc
dtoType
document
citationUrl
pageCount
1
Source metadata
id
118569128
contentType
document
title
[General Correspondence - Cicconi, Jim - 1983] [C-D]
citationUrl
identifierLocal
94
collections
Records of the Office of the Chief of Staff (Reagan Administration)
James Cicconi's General Correspondence Files
thumbnailUrl
largeImageUrl
imageCount
1
hasImages
yes
source
import
hasTranscription
no
Source extras
naId
118569128
coverageEndDate
logicalDate
1985-12-31
year
1985
coverageStartDate
logicalDate
1981-01-01
year
1981
levelOfDescription
fileUnit
recordType
description
ocrSource
nara-archive
Single page context
seq
1
pageIndex
0
type
document
mediaId
cab398270cba2977
ocrText
Cavanay
for
Rad
R
American Paper Institute, Inc.
( Powero, 315
1619 Massachusetts Avenue, NW, Washington, DC 20036
(202) 332-1050
September 13, 1983
The Honorable James W. Cicconi
Special Assistant to the President and
Special Assistant to the Chief of Staff
The White House
Washington, D.C. 20500
Dear Mr. Cicconi:
Red Cavaney asked that I forward the attached paper to you. It
Cavaney, Red (Powers, Jody)
is to replace the one he gave you this morning on Emissions Cap
Impact, Union Camp Mill - Eastover, S.C., which had many errors due
to a time constraint in getting the paper prepared.
If you should need anything further, please do not hesitate to call.
Sincerely,
Gody towers
Jody Powers
Executive Assistant
RC/jdp
Attachment
Serving the pulp, paper and paperboard industry
AMERICAN PAPER INSTITUTE MEMORANDUM
EMISSIONS CAP IMPACT
UNION CAMP MILL-EASTOVER, SC
BACKGROUND
Union Camp is constructing in Eastover, South Carolina a (paper
and pulp) mill which will commence production in September, 1984.
Construction began in 1982. As a new source located in an attainment
area for purposes of the Clean Air Act, the Eastover mill must meet New
Source Performance Standards ("NSPS") and Prevention of Significant
Deterioration ("PSD") requirements, including Best Available Control
Technology ("BACT"). Thus, the Eastover facility will meet strict air
emission limitations.
Eariler this year, Senator Stafford and Mitchell introduced acid
rain legislation (S.769 and S.145 respectively) which would cap emissions of
sulfur dioxide and nitrogen oxide, using actual emissions from 1980 as the
cap. Any facility not operating in 1980 would be required to obtain
"simultaneous (immediate) emission offsets" prior to commencing operation.
THE ISSUE
Unless new sources are exempted from the emissions cap or
unless a new baseline is adopted, clean, efficient mills like Eastover may
not be able to commence operations because SO2 and NOx offsets are not
available or not affordable.
DISCUSSION
The Mitchell and Stafford bills, as now drafted, would severely
inhibit economic growth in many states and would very possibly prevent
Union Camp's Eastover mill from ever commencing operation. It is not at
all clear that the necessary SO2 and NOx offsets are available, and offsets
are the only alternative under the legislative proposals, since it is
impossible to obtain zero emmissions from scrubbing or fuel switching. In
addition, under this legislation, the offsets are required to be made prior
to commencing operation. Thus, Union Camp's investment of $600 million
in the Eastover facility will be jeopardized by these pieces of legislation.
Even assuming that Union Camp obtained part of the SO2 and NOx offsets
needed for Eastover, the company would then be required to install
expensive and unproven additional control technology (beyond BACT) in
order to reduce emissions to the required level of offsets. Further, such
actions would be impossible to be accomplished within the time frame
("simultanteous") required by the legislation.
Penalizing, or preventing construction of efficient, clean, new
facilities like Eastover hardly constitutes wise legislative policy. Economic
growth, especially when accompanied by BACT, should not be sacrificed in
order to reduce further emissions. This is particularly true in the case of
the Eastover mill, which began construction many months ago.
CONCLUSION
Requiring SO2 and/or NOx offsets for the new Eastover mill
will delay or prevent operation of the plant, since offsets are probably not
available. API urges that new facilities be exempted from the emissions
cap and views the "simultaneous emissions offset" requirement is
particulary poor legislative policy.
fo.e.
Cavaney,
Red
-
American Paper Institute, Inc.
Government Affairs
1619 Massachusetts Ave., N.W. Wash., DC 20036/(202) 332-1050
Red Cavaney
Vice President
September 8, 1983
The Honorable James W. Cicconi
Special Assistant to the President and
Special Assistant to the Chief of Staff
The White House
Washington, D.C. 20500
Dear Jim:
Attached is a letter from my boss, Louis Laun, to Jim
Baker concerning your upcoming deliberations on acid rain.
I would appreciate the chance to visit with you for five
to ten minutes to share some specific figures which will help
illustrate the magnitude of the negative impact caused by
including industrial boilers and an emission cap in the
Administration's acid rain control package.
Hope all is well and that a highly successful fall season
Cavaney Red
is dawning. Thanks.
Warmest regards,
Bet
RC/jdp
Attachment
PI call an d
ADC
him for
bunch invite in The mest =
next wed
of he then can sched + do for
time
ge
AP
American Paper Institute, Inc.
260 Madison Avenue, New York, N.Y. 10016/(212) 340-0676
cable address: AMPAPINST New York
Office of the president
September 8, 1983
The Honorable James A. Baker III
Chief of Staff
and Assistant to the President
The White House
Washington, D.C. 20500
Dear Mr. Baker:
I understand that the Cabinet Council on Natural Resources will soon
recommend an acid rain control package to the President from among a variety
of options. Any solution will be expensive, and we feel that cost-effectiveness
should be one of the primary guiding principles in selecting a control program.
Consultations with CEQ, EPA, DOE, CEA and OPD have increased industry
concerns that the cost ramifications of several options under discussion are not
fully understood.
The lowest ratio of expenditures per yield of emission reductions is
obtained by concentrating controls on very large utility boilers due to the
economies of scale, the relative time and ease of implementation (fewer sources
per gross yield), availability of alternative power and the minimization of
differential competitive impacts within industrial sectors. Inclusion of industrial
boilers and a 1980-based emissions cap in a control program will layer excessive
costs and arbitrary expansion barriers on industry at a time when it is critical
that we increase our competitiveness in world markets. In addition, costs for
industrial boiler retrofits are likely to force the closing of many borderline
operations. If a utility boiler program is implemented, industry will doubtless be
faced with paying a share of those costs. Our industry's purchases of electricity
rank third among the nation's manufacturing industries.
Attached is a study commissioned by our industry which rebuts the
perception that controls on industrial boiler sulfur dioxide emissions through the
use of "scrubbers" are equally cost-effective with employment of the same
control measures for utility boilers. As the attached illustrates, the relative
capital cost for scrubber installation rapidly escalates for boilers smaller than
1500 million Btus. Since the bulk of our industrial boilers fall in the 10-500
million Btu range, with the largest planned only in the 900-1100 million Btu
range, industrial boilers are clearly at the least cost-effective end of the scale.
I might also point out that our study, based largely on actual installed costs,
indicates that EPA's estimates for capital costs in this area are 40 to 75% low
for industrial-sized boilers with heat inputs from 100 to 400 million Btu.
Serving the pulp, paper and paperboard industry
We also urge that you not include a 1980-based, or other, emissions cap
which would clearly inhibit economic growth and job creation by placing new
restrictions on new facilities, which are already subject to the strict new source
review provisions of the Clean Air Act.
Your assistance in including these concerns in the Administration's acid rain
deliberations is greatly appreciated.
Sincerely,
Louis Laun
Louis Laun
LFL/jrs
Attachment
50,000
NOTES: 1. FGD costs include the cost of one spare
40,000
absorber module per boiler.
FGD COST (1978 $/MBtu/hr.)
30,000
20,000
10,000
0
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
Figure 1A
1.0% SULFUR
Burns & McDonnell
LIMESTONE FGD UNIT COSTS
ENGINEERS ARCHITECTS COMBULIANTS
AT 90% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
40,000
FGD COST (1978 $/MBtu/hr.)
30,000
20,000
10,000
0
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
1.0% SULFUR
Figure 4A
Barns & McDonnell
ENGINEERS ARCHITECTS COMBULTANTS
DUAL ALKALI FGD UNIT COSTS
AT 90% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
40,000
absorber module per boiler.
FGD COST (1978 $/MBtu/hr.)
30,000
20,000
10,000
0
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
1.0% SULFUR
Figure 7A
Barns & McDonnell
SPRAY DRYER FGD UNIT COSTS
ENGINEERS ARCHITECTS COMBULIANTS
AT 90% SO2 REMOVAL
ncasi
special report
NATIONAL COUNCIL OF THE PAPER INDUSTRY FOR AIR AND STREAM IMPROVEMENT, INC., 260MADISON AVENUE, NEW YORK, N.Y. 10016
REPORT ON THE DEVELOPMENT OF FLUE GAS DESULFURIZATION
SYSTEM CAPITAL COSTS FOR VARIOUS-SIZED UNITS
SPECIAL REPORT NO. 83-06
JULY 1983
ncasi
NATIONAL COUNCIL OF THE PAPER INDUSTRY FOR AIR AND STREAM IMPROVEMENT, INC.
260 MADISON AVE. NEW YORK, N.Y. 10016 (212) 532-9000
Russell O. Blosser
Technical Director
(212) 532 9001
July 15, 1983
SPECIAL REPORT 83-06
REPORT ON THE DEVELOPMENT OF FLUE GAS DESULFURIZATION
SYSTEM CAPITAL COSTS FOR VARIOUS-SIZED UNITS
In the review of background information generated by EPA
for use in developing New Source Performance Standards for
industrial boilers, the National Council staff detected what
appeared to be a discrepancy between capital construction costs
for industrial sized boiler flue gas desulfurization systems in
an EPA contractor report and those appearing in other published
information on the costs for similar systems on utility sized
boilers.
To determine if the staff analysis was a proper one, Burns
and McDonnell, a consulting firm with extensive flue gas desul-
furization system design and capital cost experience for both
industrial and utility sized boilers, was contracted to assemble
flue gas desulfurization system costs for an array of boiler
sizes.
The attached special report was prepared directly from the
Burns and McDonnell report with supplemental elaboration by
NCASI staff. Dr. John Pinkerton, our Air Quality Program Mana-
ger, who managed this project, which was co-funded by NCASI, the
American Paper Institute and the National Forest Products Asso-
ciation, also provided the staff elaboration on the original
report.
The capital costs developed in this report for various flue
gas desulfurization systems are based on actual installed costs
wherever possible and on detailed engineering estimates other-
wise. These capital costs have been compared to flue gas desul-
furization capital cost estimates prepared by an EPA contractor.
For similar flue gas desulfurization systems with equivalent
SO₂ removal capabilities, it was found that the EPA estimates
are 40 to 75% lower than the capital costs developed in this
report for industrial sized boilers with heat inputs from 100 to
400 X 10⁶ Btu/hr.
National Council of the Paper Industry for Air and Stream Improvement 1983.
-2 -
This report did not develop information on operation and
maintenance costs. However, NCASI staff review of operating and
maintenance costs reported in EPA documents for flue gas desul-
furization systems on industrial and utility boilers reveals
that those for utility boilers are about one half those for in-
dustrial boilers. While it is not possible to identify the more
realistic of the two estimates, it is suggested that total flue
gas desulfurization costs shown in the EPA report, which was the
subject of this study, should be subject to careful review.
Your comments and inquiries are invited on matters covered
in this report and should be directed to Dr. John E. Pinkerton
or myself at the telephone or address above.
Yours very truly,
Russell O. Blosser
Technical Director
ROB:gs
Attach.
TABLE OF CONTENTS
Page
I FOREWORD
1
II INTRODUCTION
3
A. Purpose of the Report
3
B. Organization of the Report
3
III FLUE GAS DESULFURIZATION SYSTEM DESCRIPTIONS
4
A. Background and General Descriptions
4
B. Wet Limestone Flue Gas Desulfurization System
Description
5
C. Dual Alkali Flue Gas Desulfurization System
Description
6
D. Dry Lime Flue Gas Desulfurization System
Description (Spray Dryer)
6
IV COST DEVELOPMENT DESIGN CRITERIA
7
A. Purpose
7
B. General Design Criteria
7
C. Flue Gas Desulfurization System Design Criteria
9
V DEVELOPMENT OF FLUE GAS DESULFURIZATION SYSTEM
CAPITAL COSTS
19
A. Introduction
19
B. Collection and Development of Actual Cost Data
19
C. Development and Application of Cost Estimates
21
D. Flue Gas Desulfurization Capital Cost Adjustments
21
E. Flue Gas Desulfurization Capital System Costs
23
F. Further Comparison to the EPA Capital Cost
Estimates
24
VI SUMMARY AND CONCLUSIONS
25
A. Summary
25
B. Conclusions
26
C. Comparison to Radian Report
27
REPORT ON THE DEVELOPMENT OF FLUE
GAS DESULFURIZATION SYSTEM
CAPITAL COSTS FOR VARIOUS-SIZED UNITS
I FOREWORD
The Environmental Protection Agency has during the past two
or more years been assembling background information for use in
the development of New Source Performance Standards for SO₂
emission control for industrial boilers. In the review of the
cost data in this background information, the National Council
staff observed what appeared to be a major discrepancy between
construction cost estimates for flue gas desulfurization systems
for industrial boilers in a contractor report prepared for EPA
for use in development of NSPS, and published information on the
capital costs for flue gas desulfurization systems in the larger
utility boilers. In summary, the unit construction costs for
industrial boiler flue gas desulfurization systems were consis-
tently less on a common unit costing basis, than for utility
boilers. Such a situation runs counter to well known engineer-
ing cost principles in that the economy of scale factor was
absent.
To determine if the staff analysis was a proper one, Burns
& McDonnell, a consulting firm with extensive flue gas desulfur-
ization system design and capital cost experience for both in-
dustrial and utility sized boilers were contracted to assemble
flue gas desulfurization system costs for an array of boiler
sizes.
The following NCASI special report was prepared directly
from the Burns & McDonnell report. The foreword and Part F in
Section V were prepared by the NCASI staff. In those cases
where explanatory editing was carried out within the report by
the NCASI staff, this editing is underlined for identification.
The capital costs developed in this report for various flue gas
desulfurization (FGD) systems are based on actual installed
costs wherever possible and on detailed engineering estimates
otherwise. These capital costs have been compared to flue gas
desulfurization capital cost estimates prepared by an EPA con-
tractor. For similar FGD systems with equivalent SO₂ removal
capabilities, it was found that the EPA estimates are 40 to 75%
lower than the capital costs developed in this report for boil-
ers with heat inputs from 100 to 400 X 10⁶ Btu/hr. Although
apparently the EPA estimates did not include (a) redundant
equipment to insure that adequate SO₂ removal would be accom-
plished at all times, and (b) interest charges during construc-
tion, these two factors alone cannot account for all of the dif-
ferences between the two sets of cost figures. Detailed exami-
nation of additional reasons for these significant differences
was beyond the scope of this study.
- 2 -
The cost of flue gas desulfurization consists of two major
components, (a) the capital cost associated with the engineering
design, equipment purchase, and installation of the FGD system,
and (b) the expenses associated with the operation and mainte-
nance of the FGD system. This report focuses solely on the in-
stalled capital cost component because it can be quantified in
a reasonable straightforward manner compared to operating and
maintenance costs. Calculation of installed capital costs does
not require assumptions regarding (a) levels of maintenance,
(b) frequency of equipment replacement, (c) chemical usage and
price, (d) operating manpower, (e) waste disposal, (f) power
costs for system operation, (g) stack gas reheat cost, or (h)
capacity utilization, all of which are needed to arrive at an
estimate of annual operating and maintenance costs.
The EPA contractor's report does include estimates of annual
operating and maintenance expenses for FGD systems on industrial
sized boilers ranging from 30 to 400 X 10⁶ Btu/hr. Given the
observed significant differences in capital costs between the
EPA report and this report, it is logical to inquire if the EPA
operating and maintenance cost estimates are reasonable. A cur-
sory comparison of a dual alkali FGD system (90% removal effi-
ciency on a 3.5% sulfur coal) operating and maintenance cost for
the electric utility industry cited in another EPA contractor
document (EPA-450/2-78-007a, Electric Utility Steam Generating
Units - Background Information for Proposed SO₂ Emission Stan-
dards) with those for a similar industrial boiler flue gas de-
sulfurization dual alkali system estimated in the EPA/Radian
document indicates that the industrial boiler FGD operating and
maintenance cost estimate is only one-half of that for an equiv-
alent sized utility system ($0.50/106 Btu, mid-1978 dollars
for a 250 X 10⁶ Btu/hr boiler running at 60% capacity). Be-
cause of the many assumptions necessary to obtain an operating
and maintenance cost estimate, it is not possible to identify
the more realistic of the two estimates. This example compari-
son merely indicates that the operating and maintenance costs
given in the EPA document for industrial boilers are open to
question, and that any estimates for total flue gas desulfuriza-
tion costs based on the EPA document should be subject to care-
ful review.
II INTRODUCTION
A.
Purpose of the Report
The purpose of this report is to (a) present flue gas de-
sulfurization (FGD) system cost curves for three FGD processes
- 3 -
over a range of boiler sizes from 100 to 10,000 MBtu/hr, (in
this report, 1 MBtu = 10⁶ Btu), and (b) compare these costs
with similar costs presented in a recent EPA report (EPA-450/3-
82-021, August 1982). The comparison of the costs presented in
the two reports includes a discussion of the cost differences
and the possible reasons for the observed differences.
The cost curves presented in this report represent adjusted
cost data obtained from actual FGD installations and are based
on specific design criteria developed especially for this study.
The design criteria and the methodology utilized in developing
these FGD system cost curves are summarized for the purpose of
providing an accurate picture of the actual costs of FGD systems.
The FGD system cost curves also show the economy-of-scale rela-
tionship between FGD costs and boiler size.
B. Organization of the Report
The report includes a Summary and Conclusions Section which
follows the main body of the report. The body of the report is
organized into three parts as outlined below.
Section III describes the three types of FGD systems, lime-
stone, dual alkali and spray dryers, examined in this report.
The descriptions are intended to give the reader an overview of
the types of FGD processes including special characteristics and
equipment requirements for each type of FGD system.
Section IV defines the FGD design criteria necessary to de-
velop consistent cost data over the wide range of boiler sizes
examined in this report. General design criteria which apply to
all three FGD processes include site conditions, fuel analysis,
boiler specification, SO₂ removal efficiency and general equip-
ment requirements. The specific design criteria for each indi-
vidual FGD process includes the basic equipment requirements and
design criteria for that equipment.
Section V describes the methodology used in developing FGD
system costs and presents the FGD cost curves. This section
includes descriptions of (a) the sources for the actual FGD cost
data, (b) the methods by which FGD cost data were checked for
completeness and adjusted where necessary, and (c) how the data
were escalated or de-escalated to mid-1978 dollar values. The
Methodology Section also describes the cost adjustments that
were made to actual FGD cost data to account for various fuel
sulfur contents and sulfur dioxide removal efficiencies.
The FGD system capital cost curves and a discussion of the
economy-of-scale relationships for industrial and utility boiler
- 4 -
applications are presented at the end of this section. The FGD
capital cost curves summarize costs in terms of mid-1978 dollars
per MBtu/hr versus boiler size (MBtu/hr).
III FLUE GAS DESULFURIZATION SYSTEM DESCRIPTIONS
A. Background and General Descriptions
Three flue gas desulfurization (FGD) systems are examined
in this report, they are limestone and dual alkali (both wet FGD
systems), and lime spray dryers. Each of these FGD processes
works on the principle of absorption, whereby the SO₂ in the
combustion gas is transferred from the gas phase into an alkali
solution or slurry.
In wet limestone FGD systems, the absorbent is water con-
taining a suspended, only slightly soluble alkali. Therefore,
the wet limestone process is classified as a slurry system.
Alkali slurries are not easy to handle because they are abrasive
and the suspended solids tend to settle out. The products of
the absorption process also have limited solubility and may pre-
cipitate forming scale on the equipment. On the other hand,
since the products are relatively insoluble, waste disposal
is a matter of physical separation of the solids and the water.
The dual alkali FGD system is a clear liquor process which
uses a highly soluble alkali absorbent and forms soluble salts
as reaction products. The clear liquor is easy to handle and
does not settle out of solutions which greatly simplifies the
type of absorption equipment. However, since the products of
the absorption process are soluble salts, the waste disposal
process includes an extra step to produce an insoluble waste
product that can be physically separated.
The dry FGD system also utilizes water in preparing an
alkali solution or slurry. However, the amount of water
injected into the absorber is carefully controlled so that the
gas does not become saturated, allowing moisture condensation.
The dry waste product can be handled more easily by a less
complicated waste disposal system.
B. Wet Limestone Flue Gas Desulfurization System Description
In the limestone FGD process, a limestone slurry is sprayed,
usually countercurrent to the gas flow to provide contact be-
tween the slurry and the SO₂ in the gas. Once the SO₂ is
absorbed in the liquor, a number of chemical reactions take
- 5 -
place, resulting in the formation of calcium sulfite and sul-
fate. Because this process is nonregenerable, a portion of the
spent slurry is constantly purged from the process and addition-
al limestone is added.
Since the limestone system is a one-step throwaway process,
the process chemistry is much simpler than the dual alkali sys-
tem described later. The low solubility of calcium carbonate in
water, however, requires that the absorbing liquor be a slurry
of suspended limestone particles. This slurry is not easy to
handle because it is abrasive and solids will settle out forming
deposits unless constantly kept moving. The control of the
process chemistry is also critical because the reaction products
are also only slightly soluble and also tend to settle.
Because the limestone system is a slurry process, the ab-
sorption equipment is both large and complex. The absorption
equipment consists of spray tower with a high liquid flow rate
or various designs of internal packing, plates, or venturi
arrangements to maximize the gas-liquid interfacial area. The
open spray tower design is most common because of lower cost and
lack of surfaces which might plug or scale. Special attention
is required at the wet/dry interface and mist eliminators are
needed to avoid scaling and plugging. Slurry pH and density
must be fully regulated to optimize both SO₂ removal effi-
ciency and limestone utilizaton, but also to prevent scaling
and plugging.
Makeup slurry for the system is usually prepared by wet
grinding pebble-sized limestone rock. The wet grinding equip-
ment consists of a wet ball mill and a classifier arrangement to
produce a slurry as fine as 85 percent through 325 mesh (approx-
imate).
A throwaway waste product is produced by the limestone
system. The dewatering process typically includes a thickener
(hydroclones have also been used) to concentrate the solids
followed by a vacuum filter or centrifuge to dewater the sol-
ids. The FGD waste product is then mixed with boiler fly ash as
collected by a precipitator or baghouse, to provide a stabilized
sludge that can be transported via truck or conveyor to a dis-
posal area.
C. Dual Alkali Flue Gas Desulfurization System Description
The dual alkali process uses highly soluble sodium (NH₄,
Mg or Al can also be used) absorption solution followed by the
addition of lime or limestone to precipitate the sulfite and bi-
sulfite reaction waste products and regenerate the absorption
- 6 -
solution. The absorption phase of the process utilizes an aque-
ous alkaline solution to absorb the SO₂ forming soluble sulfite
and bisulfite ions. A slipstream of the recirculating absorbent
solution is treated with lime or limestone to form a calcium base
precipitate from the soluble sodium sulfite and bisulfite waste
products. The regenerated solution is then returned to the ab-
sorption loop.
Dewatering of the reacted slurry is required to separate the
calcium base precipitate from the absorbent liquor and recover
the soluble alkali liquor. The main components of the dewatering
system are the thickener and rotary vacuum filters. Slurry from
the reactor tank where lime or limestone slurry is mixed with
liquor, is fed to the thickener. Clarified liquor overflows to
the thickener hold tank prior to return to the system for pH
control. The thickener underflow slurry is pumped to the filter
system where solids separation is completed. The filter cake is
washed with fresh water to recover the soluble alkali absorbent.
The filter cake may then be transported directly to a disposal
area.
D. Dry Lime Flue Gas Desulfurization System Description (Spray
Dryer)
In the spray dryer system, an alkali reactant, in the form
of solution or slurry, is pumped to the atomizers of the spray
dryer absorber module. The atomizers are used to create a dis-
persed spray of fine droplets which are intimately mixed with
the incoming flue gas. The SO₂ contained in the flue gas is
absorbed on the surface of the droplets and the alkali material
reacts with the gas to form sulfites and sulfates. The droplets
simultaneously undergo drying and a portion of the spent solids
is collected in the base of the drying chamber. The remainder
of the solids is collected together with fly ash still entrained
in the flue gas by a fabric filter or electrostatic precipitator.
The operation of the spray dryer absorber system is con-
trolled by four process mechanisms. The first is the atomization
of the absorbent which is related to the required surface area
of the spray droplets necessary for proper drying. Intimate con-
tact between the spray droplets and flue gas is also necessary
for high SO₂ absorption rates. Similarly, proper gas disper-
sion is required for mixing and also for the prevention of moist
or wet lumps in the drying chamber. Finally, the gas residence
time, and thus the chamber size, must be sufficient to permit
maximum SO₂ absorption.
Spray dryer systems utilize solids recycle to improve sys-
tem stoichiometry (mole reactant per mole of SO₂ at the ab-
sorber inlet). The process of solids recycle involves mixing
- 7 -
a portion of the waste solids with the alkali slurry. Recycling
improves reactant utilization and takes advantage of any alka-
linity in the fly ash. Dry waste products of calcium sulfites/
sulfates and fly ash can be conveyed or pneumatically transferred
to a temporary storage silo to await transportation to a disposal
site.
IV COST DEVELOPMENT DESIGN CRITERIA
A. Purpose
Flue gas desulfurization (FGD) system capital costs are
affected by factors such as fuel analysis, sulfur removal
efficiency, gas volume, equipment included and in-service date.
In order to provide FGD costs for various boiler sizes, the
above factors are held constant by developing design criteria
for boilers, fuel, operating conditions and FGD systems. The
design criteria are applied to actual FGD system costs to pro-
vide a consistent set of FGD system cost curves. This section
includes descriptions of the general design criteria applied to
all FGD systems and specific design criteria applied to each
type of FGD system. The specific design criteria includes a
detailed summary of the equipment and design assumptions incor-
porated into each of the three FGD systems examined in this
study.
B. General Design Criteria
The general design criteria listed apply to all three FGD
systems. All FGD system costs are for new boiler installations,
because of the difficulty of estimating site specific retrofit
requirements. Equipment costs for support systems such as elec-
trical power, instrument air and make-up water are proportioned
according to requirements by the FGD system.
The predominant design criteria influencing FGD system
price is the design gas volume and sulfur dioxide mass flow
rate. The design gas volume is affected primarily by coal
analysis, amount of combustion air, gas temperature and site
elevation. Plant site elevation for this study is 500 feet
above sea level. Unlike site elevation, the other factors
affecting gas volume and sulfur dioxide concentration cannot
be held constant but will vary within a known range of values.
Good engineering practice dictates that the design gas volume
reflect this range of variation, therefore, the design gas
volumes for each case are increased by 10 percent.
- 8 -
The fuel selected for this study is bituminous coal. An
ultimate analysis for a bituminous coal was developed and used
in all combustion calculations. In order to perform combustion
calculations, the ultimate analysis for each sulfur content must
add up to 100 percent. Ash was chosen as the constituent to
vary since it has no effect on the volume of combustion gas
produced. A normal bituminous ash analysis would be expected to
vary within a range large enough to compensate for the 1.0 to
3.5 percent sulfur range indicated. The ultimate analyses
(typical of Missouri, Ohio, Illinois, and Kansas bituminous) are
shown in Table 1.
TABLE 1
ULTIMATE ANALYSIS FOR A BITUMINOUS COAL
(percent by weight)
Low Sulfur
Medium Sulfur
High Sulfur
Carbon
70.0%
70.0%
70.0%
Hydrogen
4.0%
4.0%
4.0%
Nitrogen
1.0%
1.0%
1.0%
Sulfur
1.0%
2.0%
3.5%
Water
7.0%
7.0%
7.0%
Ash
9.0%
8.0%
6.5%
Oxygen
8.0%
8.0%
8.0%
Higher Heating Value
12,000 Btu/lb
12,000 Btu/lb
12,000 Btu/lb
Boiler-related parameters affecting gas volume are combus-
tion air requirements, leakage and gas temperature. Boilers
with a thermal input rate greater than 250 MBtu/hr are pulver-
ized coal boilers. Spreader stoker boilers are used below 250
MBtu/hr. The larger pulverized coal boilers require 125 percent
total air for combustion and an air heater. Air heater leakage
is assumed to be 15 percent. The spreader stoker boilers re-
quire 130 percent total air and are not equipped with an air
heater because the economizer can serve that function. For all
boilers, the gas outlet temperature (absorber inlet design gas
temperature) is 350 degrees F.
Structural design and freeze protection are also affected
by site-related parameters. Structural design is based on an
assumed plant site located in a Seismic Zone 1 thereby elimi-
nating the need for specially designed (e.g. earthquake) founda-
tions and structures. Freeze protection is accomplished by pro-
viding metal wall panel enclosures. Enclosures offer the advan-
tages of protected maintenance and work areas at a long-term
- 9 -
cost equal to or less than the costs of heat tracing and insula-
tion.
All FGD systems include ductwork, complete with turning
vanes, internal stiffeners and insulation and lagging, to direct
combustion gases to and from the absorber modules. Included in
the limestone and dual alkali FGD costs is the ductwork from the
particulate control device outlet (excluding transitional duct-
work required to reduce cross-sectional area or connecting two
or more particulate control devices) to the absorber inlet.
Also included are bypass ductwork and ductwork from the absorber
outlet to the stack. The spray dryer FGD cost includes a simi-
lar amount of ductwork except it starts at the air heater outlet
and ends at the particulate control device inlet. Structural-
steel required to support the ductwork is included in its cost,
however, the ductwork is assumed not to be designed to support
equipment or structures connected to it such as the stack and
air heater.
Capital costs for particulate control devices, such as
electrostatic precipitator, baghouse and venturi scrubber, are
not included in the FGD system costs. Particulate removal is
required for installation regardless of whether or not a FGD
system is provided. Because particulate control costs are not
included, all three FGD system costs presented in this report
can be compared on an equal basis.
C. Flue Gas Desulfurization System Design Criteria
(1) General Each of the FGD systems described is considered
a closed-loop system producing a throwaway waste that can be
handled safely and transported to a waste disposal area. All
FGD systems include a spare absorber module and a metal wall
panel building enclosure. The limestone and dual-alkali FGD
systems include ductwork to bypass 100 percent of the gas volume
at 70 fps. The spray dryer FGD system includes bypass ductwork
for reheat only. Complete bypass capability can be accomplished
by directing gas through a nonoperating absorber module.
A spare absorber module is included with each type of FGD
system to allow steady-state, full-load operation of the boiler
without violation of sulfur dioxide emission standards if one
absorber becomes inoperative. The spare module permits main-
tenance of the inoperative absorber module with the boiler at
full load. Although this type of redundancy is not necessarily
"standard engineering practice,' it is similar to the design
philosophy for equipment which is required for full-load opera-
tion and which has a potential for frequent removal from service
for repairs.
- 10 -
(2) Wet Limestone FGD The equipment for the wet limestone
process is divided into the twelve systems described below.
(a) Absorption System This system removes sulfur dioxide from
the flue gas by contacting it with a slurry of limestone,
calcium sulfite and calcium sulfate. The Absorption Sys-
tem consists of the following equipment: (i) absorbers,
(ii) slurry recycle tanks, (iii) recycle tank mixers,
(iv) absorber recycle pumps, (v) mist eliminator wash water
tanks, (vi) wash water pumps, (vii) dampers, (viii) valves
and piping, and (ix) instruments and controls.
The absorbers are countercurrent spray towers designed for
a saturated gas velocity of 8 ft/sec and a residence time
of 5 sec. Design SO₂ removal efficiency is 90 percent
with a liquid to gas (L/G) ratio of 60 gpm/1000 cfm for low
sulfur (1 percent) fuel, 70 gpm/1000 cfm for medium sulfur
(2 percent) fuel, and 90 gpm/1000 cfm for high sulfur (3.5
percent) fuel. Towers are constructed of carbon steel with
rubber lining, except for the wet/dry interface area and
outlet ductwork which are a high nickel-chromium alloy.
Mist eliminators are pressure-molded, fiberglass-reinforced
plastic (FRP), two-stage chevrons.
Sulfur dioxide removal efficiencies of 70 and 50 percent
will be accomplished with combustion gas bypass. Utilizing
gas bypass to achieve reductions in overall removal effi-
ciency, reduces the size and cost of the entire FGD system
by the percentage of gas bypassed.
The bypass ductwork, however, is not reduced in size since
it must still bypass 100 percent of the combustion gas vol-
ume produced by the boiler.
Slurry recycle tanks are covered, carbon steel tanks with
organic, corrosive-resistant linings. A separate tank,
sized for a slurry hold time of 10 minutes, is required for
each absorber tower.
Absorber recycle pumps are rubber-lined centrifugal pumps;
two 100 percent capacity pumps are provided when the design
slurry flow rate can be handled by one pump and three 50
percent capacity pumps when two pumps are required to han-
dle the design flow rate. When three or more pumps are
required to provide the design slurry flow, spare capacity
pumps are not provided. Instead, the total capacity of the
pumps is increased to greater than 100 percent of the de-
sign slurry flow. Slurry piping is rubber-lined carbon
steel.
- 11 -
(b) Limestone Handling System - This system transports lime-
stone from the rail car or truck unloading point to the
ready pile and from the ready pile to storage silos where
it is stored until dispensed for production of limestone
slurry. The Limestone Handling System includes the follow-
ing equipment: (i) limestone unloading hopper, (ii) lime-
stone unloading hopper gate valves, (iii) limestone unload-
ing hopper vibrating feeders, (iv) belt conveyors and/or
bucket elevators, (v) conveyor galleries, (vi) belt scales,
(vii) belt conveyor magnetic separators, (viii) limestone
lowering well, (ix) limestone ready pile reclaim hopper,
(x) limestone ready pile dischargers, (xi) limestone ready
pile vibrating feeders, (xii) limestone storage silo,
(xiii) limestone silo bin dischargers, (xiv) limestone
storage silo flop gate, (xv) limestone storage silo dust
collectors, (xvi) ventilation system, and (xvii) instru-
ments and controls.
Limestone can be stored on site in an uncovered pile for
long-term storage; therefore, the limestone storage silo
provides three days' storage. The smaller capacity systems
utilize a bucket elevator to transfer limestone from long-
term storage to the limestone storage silo.
(c) Limestone Preparation System - This system wet grinds the
limestone and delivers the slurry obtained to the Absorp-
tion System. The Limestone Slurry System includes the
following: (i) limestone weigh feeders, (ii) ball mills,
(iii) mill product tanks, (iv) classifiers, (v) mill prod-
uct pumps, (vi) limestone slury storage tanks, (vii) lime-
stone slurry transfer pumps, (viii) piping and valves, and
(ix) instruments and controls.
It is assumed that this system includes two 100 percent
capacity ball mills complete with classifiers to produce a
30 percent suspended solids limestone slurry product with
85 percent of the solids less than 325 mesh. The slurry
storage tank provides a two-day limestone slurry storage
capacity.
(d) Oxidation Air System - This system provides low-pressure
(18-psig) compressed air to the oxidation tanks to oxidize
the suspended solids in the waste slurry from calcium sul-
fite (CaSO₃) to calcium sulfate (CaSO₄ gypsum). The
sulfate crystals settle faster and dewater easier than the
sulfite crystals. Also, the sulfate compound produced is
a more easily handled waste product. The Oxidation Air
- 12 -
System consists of the following: (i) intake filter silen-
cers, (ii) forced oxidation air compressors (centrifugal),
(iii) blowoff silencers, (iv) instruments and controls, and
(v) piping and valves.
(e) Waste Slurry System This system transfers the overflow
from the absorber reactor tanks through the forced oxida-
tion tanks to the thickener. The system also includes the
emergency hold tank and a drainage sump. The Waste Slurry
System includes the following: (i) waste slurry tank,
(ii) waste slurry tank agitator, (iii) waste slurry trans-
fer pumps, (iv) waste slurry sump, (v) waste slurry sump
agitator, (vi) waste slurry sump pumps, (vii) oxidizer feed
tank, (viii) oxidation tanks, (ix) thickener feed tank,
(x) emergency hold tank, (xi) emergency hold tank pumps,
(xii) piping and valves, and (xiii) instruments and con-
trols.
(f) Sludge Dewatering System - This system concentrates and
dewaters the suspended solids present in the absorber waste
slurry for further processing and final disposal by the
Sludge Handling System. Concentration, or thickening,
takes place in a round mechanical lift thickener with de-
watering occuring in a single-stage vacuum filter. Various
building drainage sumps are also included in the Disposal
System. The Sludge Dewatering System includes the fol-
lowing: (i) thickener, (ii) thickener underflow pumps,
(iii) fabric vacuum filters, (iv) belt conveyors, (v) thick-
ener tunnel, pug mill and sludge dewatering building sump
pumps, (vi) pug mill and sludge dewatering building sump
mixers, and (vii) instruments and controls.
It is assumed that this system includes one 100 percent
capacity thickener to produce a 30 percent solids under-
flow. A spare thickener is not required because of the
storage capacity available in the emergency hold tanks.
Fabric vacuum filters (including one spare) produce a 50
percent solids sludge cake from the thickener underflow.
(g) Sludge Handling System This system transforms the sulfur
dioxide (SO₂) scrubber sludge and fly ash into a product
suitable for final disposal. The Sludge Handling System
consists of the following equipment: (i) belt conveyors and
scales, (ii) fly ash silo knife gates and rotary feeders,
(iii) pug mills, (iv) pug mill dust collectors, and (v) in-
struments and controls.
It is assumed that this system produces a stable waste
material for transportation off site.
- 13 -
(h) Gas Cleaning and Sludge Dewatering Control System - The
Control System automatically controls the gas cleaning
equipment and associated fluids as required to maintain
flue gas emissions within the gas cleaning system specifi-
cations, and disposes of waste products generated by these
systems. The Gas Cleaning and Sludge Dewatering Control
System is contained in an air-conditioned and heated con-
trol room in the FGD enclosure and consists of the follow-
ing components: (i) gas cleaning control board, (ii) Sludge
Handling System control board, (iii) analog controls,
(iv) logic controls, (v) control switches, lights, operat-
ing stations, recorders and indicators, (vi) analyzers,
transmitters, controllers, control drives, valves and
alarms, and (vii) events recorder with printer.
(j) Reclaimed Water System - This system recycles clarified
process water and provides liquid storage capacity within
the closed-loop absorber and scrubber sludge dewatering
handling system. The Reclaimed Water System includes the
following: (i) reclaim water tank, (ii) reclaim water
pumps, (iii) valves and piping, and (iv) instruments and
controls.
(3) Auxiliary Systems - The following systems are required for
proper operation of the FGD system.
(a) Makeup Water System - This system provides good quality
water for various process and equipment uses in the ab-
sorber and sludge dewatering systems which cannot utilize
reclaim water. The source of makeup water is the plant
service water or cooling water systems. The makeup water
system provides water for the following systems and uses:
(i) mist eliminator wash, (ii) absorber inlet and outlet
isolation damper flush, (iii) solids disposal system,
(iv) reclaim water system, (v) pump seal water, (vi) cool-
ing water to various pieces of equipment, (vii) fly ash
wetting in the dustless unloader, and (viii) scrubber
sludge and fly ash wetting in the pug mills.
(b) System Seal Water - This system provides seal water to
pumps in the FGD system. The Seal Water System consists
of the following equipment: (i) seal water tank, (ii) seal
water pumps, (iii) seal water strainer, and (iv) valves and
piping.
(c) System Instrument Air - This system distributes clean, dry
air from the plant compressed air system to operate control
- 14 -
valves, solenoid valves and other instruments in the ab-
sorber, reagent preparation and waste handling areas. This
system includes: (i) compressed air receiver tank, (ii) air
filters, and (iii) piping and valves.
(4) Dual-Alkali FGD - The equipment for the Dual-Alkali FGD
System is separated into the ten systems described below.
(a) Absorption System - This system removes sulfur dioxide from
the combustion gas by contacting it with a highly soluble
soda ash solution. The Absorption System consists of the
following equipment: (i) absorbers, (ii) absorbent solution
recycle tanks, (iii) recycle tank mixers, (iv) absorber re-
cycle pumps, (v) mist eliminator wash water tanks, (vi) wash
water pumps, (vii) dampers, (viii) valves and piping,
(ix) instruments and controls, (x) soda ash silo, (xi) soda
ash bin dischargers, and (xii) rotary feeder.
The absorbers will be tray type constructed of lined carbon
steel or stainless steel. The absorbers are designed for a
liquid to gas (L/G) ratio of 10 gallons per thousand acf
saturated at 130 degrees F and a gas velocity of 8 fps
through the absorber. The Dual-Alkali System will achieve
90 percent removal with a 10 percent soda ash solution.
Removal efficiencies of 70 and 50 percent will be accom-
plished with combustion gas bypass.
The Dual-Alkali Absorption System will be provided with a
soda ash storage silo sized for a 5-day emergency feed
rate. The emergency feed rate will occur when the sludge
solids wash system is nonoperative. During emergency con-
ditions, approximately 10 percent of the sodium ion is
leaving the system in the sludge cake while under normal
conditions, (i.e. with solids washings) only about 2 per-
cent of the soluble sodium ion leaves the system. Under
normal conditions, the soda ash silo provides 30 days
storage.
(b) Quicklime Handling System - This system unloads pebble
quicklime from rail cars and/or trucks, and pressure
conveys the product to storage silos. The Quicklime Han-
dling System includes the following: (i) unloading hopper,
(ii) unloading filter/receiver, (iii) rotary feeders,
(iv) unloader vacuum pumps, (v) unloader pressure blower,
(vi) transfer blowers, (vii) quicklime silos, (viii) bin
dischargers, (ix) pneumatic conveyor piping, (x) blower
filters and silencers, (xi) bin vent filter fans and fil-
ters, and (xii) diverter valves, control valves, instru-
ments and controls.
- 15 -
The quicklime handling system silo will provide 30-day
on-site storage.
(c) Regeneration System - This system precipitates the soluble
sodium sulfite and bisulfite waste products from the ab-
sorption system recirculating loop. The Regeneration Sys-
tem includes the following equipment: (i) quicklime silo,
(ii) lime silo bin vibrator, (iii) lime weigh feeder,
(iv) lime slaker, (v) silo vent filter fans and filter,
(vi) reactor tank, (vii) reactor tank agitator, (viii) emer-
gency hold tank and pumps, (ix) thickener feed pumps, and
(x) instruments and controls.
The following assumptions apply:
The Regeneration System will utilize pebble quicklime pro-
viding 90 percent lime utilization in the regeneration
process at a 10-minute retention time in the reaction
tank. The lime preparation system will include two 100
percent capacity slakers and a feed system. The lime pre-
paration feed silo will provide a minimum of 10 days stor-
age. For the smaller units burning low sulfur coals, bulk
storage will not be required because the lime preparation
feed bin can be sized to hold the 30-day lime requirement.
(d) Sludge Dewatering System - This system concentrates and
dewaters the suspended solids present in the Regeneration
System slurry for further processing and final disposal by
the Sludge Handling System. Concentration or thickening
takes place in a round mechanical lift thickener with de-
watering occurring in a single-stage vacuum filter. Var-
ious building drainage sumps are also included in the Dis-
posal system. The Sludge Dewatering System includes the
following: (i) thickener, (ii) thickener underflow pumps,
(iii) fabric vacuum filters with wash system, (iv) belt
conveyors, (v) thickener tunnel, pug mill and sludge
dewatering building sump pumps, (vi) pug mill and sludge
dewatering building sump mixers, (vii) instruments and
controls, and (viii) absorbent solution return pumps.
The Sludge Dewatering system will be equipped with a 100
percent capacity thickener producing 30 percent suspended
solids. A spare thickener is not required because of the
storage available in the emergency hold tanks. Fabric
vacuum filters (including one spare) produce a 50 percent
solids cake for transportation off site. The fabric vacuum
filters are equipped with a filter cake wash system to
recover soluble alkali absorbent.
- 16 -
(e) Sludge Handling System - This system serves the same pur-
pose and includes the same equipment as described for the
Wet Limestone FGD system.
(f) Gas Cleaning and Sludge Dewatering Control System - This
system serves the same purpose and includes the same equip-
ment as described for the Wet Limestone FGD system.
(g) Auxiliary Systems - The following systems each serve the
same purpose and include the same equipment as described
for the Wet Limestone FGD system which includes: (i) makeup
water system, (ii) seal water system, and (iii) system in-
strument air.
(5) Dry Lime FGD (Spray Dryer) - Equipment for the dry lime FGD
is separated into the systems described below.
(a) Absorption System - This system removes sulfur dioxide from
the combustion gas by contacting it with a dispersed spray
of fine lime slurry droplets. The absorption system in-
cludes the following equipment: (i) absorbers, (ii) reheat
ductwork, (iii) slurry feed tank, (iv) slurry feed pumps,
(v) slurry atomizers, (vi) dampers, (vii) valves and
piping, and (viii) instruments and controls.
The spray dryer system will utilize a liquid to gas ratio
of 0.3-gallon per 1,000 scf, have a design gas velocity
through the absorber of 3 fps and a 12-second gas residence
time. The towers and ductwork are constructed of carbon
steel. Reheat via gas bypass ductwork is required to keep
the treated gas above its dew point, thereby eliminating
the possibility of moisture condensation which would ad-
versely affect the performance of the downstream particu-
late removal device.
Stoichiometry for the process is based upon a 20 degree F
approach temperature to saturation and varies with the SO₂
inlet concentration, percent removal and solids recycled as
shown on Table 2. The stoichiometry requirements presented
in Table 2 are not intended to be representative of a manu-
facturer's guaranteed lime stoichiometry. Rather, they re-
present design values appropriate for use in sizing reagent
preparation and related equipment. A minimum stoichiometry
requirement of 0.7 mole of lime per mole of SO₂ at the
absorber inlet is applied to all cases. Slurry recycle is
not employed unless required to achieve the required per-
cent SO₂ removal (high sulfur and 90 percent removal).
- 17 -
TABLE 2
DESIGN STOICHIOMETRY REQUIREMENTS FOR SPRAY DRYER
% S
SO₂ ppm
% SO₂
Stoichiometry
Fuel
(Wet)
Removal
Required
50
0.7
1%
700 ppm
70
0.9
90
2.0
50
0.7
2%
1400 ppm
70
1.0
90
2.2
50
0.8
3.5%
2600 ppm
70
1.3
90
2.0 (R)
(R) - 50 percent recycle of sorbent with lime, assumes
no alkalinity fly ash.
(b) Quicklime Handling System - This system unloads pebble
quicklime from rail cars and/or trucks, and pressure conveys
the product to storage silos. The Quicklime Handling Sys-
tem includes the following: (i) unloading hopper, (ii) un-
loading filter/receiver, (iii) rotary feeders, (iv) unloader
vacuum pumps, (v) unloader pressure blower, (vi) transfer
blowers, (vii) quicklime long-term storage silos, (viii) bin
dischargers, (ix) pneumatic conveyor piping, (x) blower fil-
ters and silencers, (xi) bin vent filter fans and filters,
and (xii) diverter valves, control valves, instruments and
controls.
The Quicklime Handling System will provide 30 days' on-site
storage.
(c) Lime Preparation System - The Lime Preparation System pro-
vides lime slurry for use in the absorption system. The
system includes the following equipment: (i) quicklime
silo, (ii) lime silo bin vibrator, (iii) lime weigh
feeders, (iv) lime slakers, (v) mill product tanks,
(vi) classifiers, (vii) mill product pumps, (viii) lime
slurry hold tanks, (ix) lime slurry transfer pumps,
(x) piping and valves, and (xi) instruments and controls.
- 18 -
The Lime Preparation System includes a minimum 10-day-capa-
city lime silo. Packaged lime preparation systems can be
utilized for storage capacities less than 5,000 ft³. As
was the case for the dual-alkali FGD system, some small
units are capable of 30 days storage in the lime prepara-
tion feed bin. Two lime slakers (one 100 percent backup)
with a 3:4 water to lime ratio produce a 10 percent sus-
pended solids slurry. The lime slurry hold tank is sized
for 30-minute retention to allow for lime stabilization.
(d) Slurry Recycle System - When required, this system recycles
approximately 50 percent of the waste product to increase
lime utilization. The system includes the following equip-
ment: (i) waste product storage tank, (ii) screw conveyor,
(iii) slurry recycle tank, (iv) slurry recycle tank mixers,
and (v) slurry recycle pump.
(e) Gas Cleaning and Waste Handling Control System - - The Gas
Cleaning and Waste Handling Control System automatically
controls the gas cleaning equipment and associated fluids
as required to maintain flue gas emissions within the
cleaning system specifications, and disposes of waste prod-
ucts generated by these systems. This System consists of
the following components: (i) gas cleaning control board,
(ii) waste handling system control board, (iii) analog con-
trols, (iv) logic controls, (v) control switches, lights,
operating stations, recorders and indicators, (vi) analy-
zers, transmitters, controllers, control drives, valves and
alarms, and (vii) events recorder with printer.
(f) Waste Handling System - This system transports dry absorber
waste from the absorber hopper to a storage silo to await
transportation to a disposal area. This system utilizes
much of the same equipment required by the ash handling
system. The cost of this system reflects the cost of
equipment and additional equipment capacity required spe-
cifically for the FGD system. Equipment costs include:
(i) absorber hopper intake valves, (ii) pneumatic conveyor
piping, (iii) diverter valves, and (iv) instruments and
controls.
Additional equipment capacity costs include: (i) transfer
blower capacity and (ii) storage silo capacity.
(g) Auxiliary System These systems each serve the same pur-
pose and include the same equipment as described for the
- 19 -
Wet Limestone FGD system which include: (i) makeup water
system, (ii) seal water system, and (iii) system instrument
air.
V DEVELOPMENT OF FLUE GAS DESULFURIZATION SYSTEM
CAPITAL COSTS
A.
Introduction
Flue Gas Desulfurization (FGD) System capital costs were
developed for limestone, dual-alkali and spray-drying FGD pro-
cesses for installation on coal-fired boilers ranging in size
from 100 to 10,000 MBtu/hr. For each type of FGD process, two
sets of costs were developed: (a) costs for coal sulfur con-
tents of 1.0, 2.0 and 3.5 percent, and (b) sulfur dioxide re-
moval efficiencies of 50, 70 and 90 percent.
The FGD System costs for each set were based on actual in-
stalled costs, where available, and on estimated costs developed
especially for this study. Both actual and estimated costs were
developed to reflect the design criteria outlined in Section IV.
Actual cost data were adjusted upward or downward to arrive at
costs for the nominal sulfur and removal efficiency percentages
identified.
The following sections describe the methodology used in the
development of actual costs, cost estimates and cost adjustments.
B. Collection and Development of Actual Cost Data
(1) Actual Cost Data - The FGD system cost curves presented in
this report are based primarily on actual cost data for indus-
trial and electric utility applications. The extensive use of
actual FGD costs required the ability to (a) identify and sepa-
rate costs into FGD systems or components and, (b) establish an
index year for the costs. These prerequisites were established
so that actual costs could be adjusted for the design criteria
defined in Section IV and corrected to mid-1978 dollar values.
Actual FGD system cost data were obtained from both Burns &
McDonnell FGD projects and other sources. Burns & McDonnell FGD
projects include eleven limestone FGD systems ranging in size
from 750 to 6700 MBtu/hr and two spray dryer systems at 175 and
6700 MBtu/hr. Additional sources of FGD cost data included data
from the EPA Utility Flue Gas Desulfurization Information System
Data Base and information published by owners and manufacturers
concerning actual installed FGD system costs. These sources
provided costs for a 200 MBtu/hr spray dryer and dual alkali
systems at 200, 1200 (2 systems), and 4,000 MBtu/hr.
- 20 -
(2) Cost Identification - As indicated earlier, the usefulness
of actual FGD system costs depends on the availability of a de-
tailed system description and cost breakdown. A detailed system
description includes, for example, information concerning the
amount of sulfur in the fuel, percent sulfur dioxide removal,
gas volume treated, size of the boiler served, percent gas by-
pass, and in-service date. A detailed cost breakdown includes
information concerning not only the costs of equipment and in-
stallation but also equipment size, equipment redundancy, and
special materials of construction.
The detailed system cost breakdown prepared for this report
to use in checking actual cost data for completeness includes
the breakdown of direct construction costs and indirect costs.
Direct construction costs include the cost of material and
installation for: (i) FGD absorbers, (ii) ductwork and dampers,
(iii) reagent preparation equipment, (iv) FGD enclosure and
structures, (v) foundation and substructures (vi) sludge de-
watering equipment, (vii) process piping and pumps, (viii) power
wiring and electrical equipment, (ix) instruments and controls,
(x) site preparation, and (xi) painting, paving, cleanup and
miscellaneous.
Indirect costs include the costs of: (i) engineering costs,
and (ii) interest during construction.
Taxes were not included as an indirect cost of the FGD sys-
tems since pollution control equipment is generally tax exempt.
(3) Cost Indexing - Following the identification and breakdown
of actual FGD costs into direct construction and indirect costs,
all cost data were either escalated or de-escalated according
to the date for which the costs were reported. The cost adjust-
ment factors used to correct costs to mid-1978 values appear in
Table 3. The cost adjustment factors are derived from the
weighted average of several indices. The indices include those
commonly used in Burns & McDonnell FGD absorber and related
contracts for labor and material escalation, the Handy Whittman
Indicies for Utility Boiler-Erected Structural Steel and Labor
Crafts, and applicable indices for electrical and control wiring
and equipment, pumps and piping. The cost adjustment factors
were submitted to several FGD suppliers and found to be repre-
sentative of the actual cost escalation experienced by these
suppliers.
- 21 -
TABLE 3
COST ADJUSTMENT FACTORS
Year
CA Factor
Year
CA Factor
Mid-1973
0.57
Mid-1978
1.00
Mid-1974
0.73
Mid-1979
1.09
Mid-1975
0.81
Mid-1980
1.19
Mid-1976
0.85
Mid-1981
1.29
Mid-1977
0.91
Mid-1982
1.37
C.
Development and Application of Cost Estimates
Cost estimates were developed primarily to provide contin-
uous cost curves for the FGD systems as defined in Section IV of
this report, for boilers ranging from 100 to 10,000 MBtu/hour.
Cost estimates were provided for equipment or FGD systems that
were excluded according to the detailed system cost breakdowns
for actual FGD costs. Cost estimates were also developed for
entire FGD systems when no actual FGD cost data was available.
All estimated cost data are based on Burns & McDonnell FGD
projects, cost data for similar-sized equipment and equipment
manufacturer's data or were prepared by Burns & McDonnell's
Estimating Department given the design criteria in Section IV
for FGD applications. Again, all cost estimates were corrected
to mid-1978 dollars before being added to FGD system costs.
D.
Flue Gas Desulfurization Capital Cost Adjustments
The final stage in the development of FGD capital costs
involved adjustments to provide costs for 1.0, 2.0, and 3.5
percent sulfur and 50, 70, and 90 percent sulfur dioxide removal
efficiency at a known boiler size. Adjustments were made for
gas volume, percent sulfur and percent SO₂ removal.
(1) Adjustment for Gas Volume - Each of the actual FGD systems
examined for this report have absorber modules which were sized
to a certain design gas volume as determined on a plant by plant
basis. Before using the actual FGD cost data, it is necessary
to convert the actual design gas volume into an equivalent
boiler size based on the assumed parameters for site elevation,
fuel analysis, combustion air, leakage and gas temperature as
defined in Section IV. The adjustment for gas volume is
accomplished by dividing each FGD design gas volume by a
constant correction factor, with the units of actual cubic feet
per MBtu.
- 22 -
The reason for this adjustment is that the actual cost data
was based on design parameters which do not coincide with the
design assumptions of the study.
The adjustment results in an equivalent boiler size in
MBtu per hour at which 100 percent of the design gas volume is
treated. For FGD systems with two or more absorber modules, but
without a spare absorber module at the design gas volume, one of
the modules is designated as a spare and the design gas volume
reduced accordingly. This adjustment results in an equivalent
boiler size that includes a spare FGD module. The cost of this
FGD system is then corrected to reflect reduced reagent and
sludge handling requirements.
(2) Adjustment for Percent Sulfur - Sulfur content directly
affects waste solids production and reagent requirements. Cost
adjustments for sulfur contents of 1.0, 2.0, and 3.5 percent
sulfur reflect equipment changes in reagent handling, reagent
preparation, Absorption System's slurry recycle (L/G require-
ments), Sludge Dewatering System and Sludge Handling System.
Variations in sulfur content also have a slight effect on con-
trol systems, piping, and electrical wiring by virtue of equip-
ment requirements. However, these cost changes are judged neg-
ligible in comparison to the changes in equipment costs and,
therefore, have not been included in the adjustments.
(3) Adjustment for Percent Removal Efficiency - As indicated
earlier, the adjustment for gas volumes resulted in the cost for
a FGD system that treats 100 percent of the combustion gas with
one spare module. From this cost data, adjustments are made to
provide costs for FGD systems with 70 percent and 50 percent
sulfur dioxide removal efficiencies.
For limestone and dual-alkali FGD systems, lower percent
removal efficiencies are accomplished with combustion gas bypass.
The amount of combustion gas bypass required for a FGD system
with a design SO₂ removal efficiency of 90 percent, as defined
by the FGD design criteria in Section IV, is shown in Table 4.
TABLE 4
EQUIVALENT SULFUR DIOXIDE REMOVAL EFFICIENCIES
FOR A KNOWN AMOUNT OF COMBUSTION GAS BYPASS
Equivalent SO₂
Combustion Gas
Removal Efficiency
Bypass Percentage
90
0
70
22
50
44
- 23 -
The amount of combustion gas bypass indicated in Table 4
gives an indication of the reduction in size of all FGD systems
(and costs) except for bypass ductwork and ID fans.
For spray dryer systems, adjustment of the SO₂ removal
efficiencies is accomplished by the adjustment of system stoi-
chiometry. Stoichiometry requirements are shown on Table 2.
Increasing system stoichiometry increases the cost of all spray
dryer systems and equipment except for ductwork, ID fans, and
the absorber module. Stoichiometry requirements also indicate
the desirability of solids recycle at high sulfur and high re-
moval efficiency. Consequently, spray dryer FGD system costs,
at 3.5 percent sulfur and 90 percent removal, include the addi-
tional cost of the Slurry Recycle System.
E. Flue Gas Desulfurization Capital System Costs
FGD capital costs are presented in the attached Figures 1,
2, and 3 limestone FGD unit costs, Figures 4, 5, and 6 dual-
alkali FGD unit costs, and Figures 7, 8 and 9 spray dryer FGD
unit costs. All FGD system capital costs are summarized by cost
curves representing mid-1978 dollars per million Btu per hour
versus boiler size in million Btu per hour heat input. Pre-
sented in this form, the phenomenon known as "economy of scale"
is dramatically demonstrated.
In addition to the cost curves, flue gas desulfurization
system costs are also summarized in Table 5. Table 5 presents
FGD cost percentages broken down for material, installation,
engineering and interest during construction at several different
boiler sizes. It should be noted that interest during construc-
tion is not dependent on unit size but rather is totally depen-
dent on the terms of financing used. Actual cost data provided
costs for interest during construction within a range of 20 per-
cent to 30 percent of total FGD costs.
Included in all of the FGD cost percentages summarized in
Table 5 is the cost of redundant equipment. Redundant equipment
is described in Section IV as equipment for which providing re-
dundancy is not "standard engineering practice,' but spare capa-
city required for continuous full-load operation. This includes
the spare absorber module and the spare equipment capacities, as
described in Section IV, for the reagent preparation and the
sludge dewatering systems. The cost of redundant equipment, as
a percentage of total FGD system costs, varies slightly with the
size of the system. For example, the cost of redundant equip-
ment for unit sizes of 1,000 MBtu/hr and less vary within the
range of 20 percent to 25 percent of the total FGD system costs.
For a unit size of 6,000 MBtu/hr the cost of redundant equipment
is within the range of 10 percent to 15 percent of the total FGD
system cost.
- 24 -
TABLE 5
FGD COMPONENT COSTS AS A PERCENTAGE OF FGD SYSTEM
CAPITAL COSTS AT GIVEN BOILER SIZE
Component
Boiler Size (MBtu/hr
200
2000
4000
6000
Equipment, Material
and Structures
37%
41%
45%
45%
Erection, Installation
and Contractor Fees
30%
27%
24%
24%
Engineering and Start-up
8%
7%
6%
6%
Interest During Construction
25%
25%
25%
25%
F.
Further Comparison to the EPA Capital Cost Estimates
As discussed earlier, the capital cost estimates contained
in the EPA document "Costs of Sulfur Dioxide, Particulate Mat-
ter, and Nitrogen Oxide Controls on Fossil Fuel Fired Industrial
Boilers" are significantly lower than those shown in Figures 1
through 9. In the EPA report, FGD cost estimates are given for
dual alkali and spray dryer systems for model boiler sizes of 30,
75, 150 and 400 MBtu/hr. For the dual alkali FGD systems, re-
moval efficiencies of 50 and 90% were considered for coals with
sulfur contents of 3.54 and 0.6%. For the spray dryer, costs
were only developed for a 50% removal efficiency for a 0.6%
sulfur coal.
It is illustrative to graphically compare the EPA cost
estimates to those developed in this report for similar FGD
systems and removal efficiencies. These comparisons are shown
in Figure 10 (dual alkali systems, 90% SO₂ removal), Figure 11
(dual alkali system, 50% SO₂ removal), and Figure 12 (spray
dryer, 50% removal). The EPA cost figures were taken from
Tables 3-1 and 3-2 in the Radian report for the dual alkali sys-
tems which did not include particulate matter control as part of
the SO₂ control costs. Spray dryer costs were estimated from
Table 3-2 by subtracting the fabric filter cost (to be consis-
tent with the Burns & McDonnell costs) from the combined SO₂
and particulate matter control cost. All costs were normalized
to mid-1978 dollars per 10⁶ Btu/hr boiler heat input.
Figures 10 through 12 show the EPA capital cost estimates
are lower than those developed by Burns & McDonnell by factors
of roughly 2.5 to 4. Although costs for some redundant equipment
and interest charges during construction were included in the
- 25 -
Burns & McDonnell cost estimates but apparently not in the EPA
values, these two factors are not nearly great enough to account
for the large observed differences. While it is beyond the
scope of this study to identify why the EPA cost figures are so
much lower, it seems likely the Radian cost algorithms do not
realistically reflect installed costs of dual alkali and spray
dryer FGD systems experiences at a number of actual facilities.
VI SUMMARY AND CONCLUSIONS
A. Summary
(1) This report presents capital costs developed from actual
installed cost data for three flue gas desulfurization (FGD)
systems, limestone, dual alkali and spray dryer. The costs were
developed for the purpose of comparison to similar costs pre-
sented in a recent report prepared by the Radian Corporation for
the U.S. Environmental Protection Agency titled, Costs of Sulfur
Dioxide, Particulate Matter and Nitrogen Oxide Controls on Fossil
Fuel-Fired Boilers (EPA-450/3-82-021).
(2) The FGD system costs presented in this report are for bi-
tuminous coals with sulfur contents of 1.0, 2.0 and 3.5 percent,
and for sulfur dioxide removal efficiencies of 50, 70 and 90 per-
cent over a range of boiler sizes from 100 to 10,000 MBtu/hr.
(The cost of redundant equipment is included in the cost esti-
mates. Redundant equipment is defined as spare capacity equip-
ment needed for continuous operation of the FGD system, beyond
the equipment judged necessary for "good engineering prac-
tice"). To provide consistent cost data over the range of
boiler sizes, all costs are corrected to mid-1978 dollars and
are based on design criteria developed especially for this
study. The design criteria define the process systems and
equipment included in the costs for each type of FGD system and
allow for adjustment of cost estimates to account for items not
included in the costs of actual installed FGD systems.
(3) The costs of particulate control devices for any of the
three FGD systems examined are not included in this report.
Particulate control devices are required for coal-fired boilers
regardless of whether or not a FGD system is provided. Often,
as in the case of the Radian report, the cost of a particulate
control device is included in the cost of spray dryer FGD sys-
tems, because it is considered an integral part of the system.
However, particulate removal is equally important for a wet FGD
system because of the adverse effect of particulate on absorber
performance and maintenance. Because particulate removal is not
included, all three FGD system costs are compared on an equal
basis.
- 26 -
(4) In general, the cost of particulate control equipment de-
pends on the type of equipment employed and the particulate re-
moval efficiency required. The two most common types of equip-
ment for collecting the relatively small-sized fly ash particles
from coal-fired boilers are electrostatic precipitators and bag-
houses. Both of these types can be designed for the high removal
efficiency which is commonly required to meet state and Federal
particulate emission standards. Although the cost of a complete
particulate control system depends on the size of the boiler,
the type of equipment selected and the degree of conservation
exercised by the designer, the cost of a complete particulate
control system is estimated to range from 30 to 85 percent of
(and in addition to) the cost of the FGD system. This estimate
is based on achieving an emission rate of 0.051b/MBtu which is
the particulate emission limitation expected to be proposed for
new coal-fired industrial boilers. The exact cost of particulate
control equipment depends on the various factors involved and
must be determined on a case-by-case basis.
(5) FGD system costs are presented in the form of mid-1978 dol-
lars per MBtu/hr versus boiler size in MBtu/hr. In this form,
the economy of scale relationships between FGD system cost and
boiler size is easily demonstrated. Unit costs (dollars per
MBtu/hr) are larger for smaller boilers than larger boilers.
B. Conclusions
(1) The FGD system for a limestone FGD system is slightly
greater than for a dual alkali FGD system, while the spray dryer
FGD system is the least expensive. The primary reason for the
cost differences is the complexity of the design and equipment
required for the absorption modules and absorbent pumps and
piping. In addition, the spray dryer FGD system requires less.
waste handling equipment than either the dual alkali or lime-
stone FGD system.
(2) It should be noted that while the FGD system costs pre-
sented in this report are representative of actual installed
costs, they cannot be asumed to represent the cost of any spe-
cific FGD system. Factors affecting FGD system costs such as
site specific requirements, competitive bidding, regional econ-
omic conditions and local and state air pollution regulations
cannot be included in a study of this nature. However, by
limiting some of the cost variables identified in this report
and by defining general and specific design criteria for the FGD
systems, the resulting FGD system costs are as representative as
reasonably can be expected.
- 27 -
C. Comparison to Radian Report
(1) The Radian report presents costs for dual-alkali and spray
dry FGD systems for application on coal-fired boilers. Dual-
alkali system costs are for coals at high sulfur (3.54 percent)
and low sulfur (0.6 percent) and removal efficiencies of 50 and
90 percent. The spray dryer system costs are for low-sulfur
coal at a 50 percent removal efficiency.
(2) Costs for both of these FGD systems were derived from equa-
tions (cost algorithms) developed by the Acurex Corporation based
on cost information contained in an earlier Radian Corporation
report. The Radian report does not state exactly what equipment
costs are included in the algorithms although the report indi-
cates that the algorithms provide "
total direct costs without
prior computation of equipment and installation costs." (Appar-
ently the Radian estimates do not include the cost of any redun-
dant equipment). Flue gas desulfurization costs based on the
algorithms are lower than the costs presented in this report.
(3) The Radian report does include general design criteria for
the FGD systems identified. However, the criteria are limited
to absorber type, materials of construction, pressure drop and
liquid-to-gas ratio. This report attempts to more clearly de-
fine each FGD system process and the equipment required.
(4) The Radian report contains costs for a shop-assembled
"package" and field-erected coal-fired boilers, however, the
report does not indicate if any FGD systems are shop assembled.
The use of shop-assembled equipment offers a cost advantage over
field erection and is used to some extent on all sizes of sys-
tems. On a small industrial boiler FGD system, for example, a
package lime preparation system (including reagent silo, slakers,
slurry tank, pumps and piping) may be purchased shop assembled,
while the absorber tower and other equipment may be too large to
assemble off site. Even large FGD systems may have shop-assem-
bled units, such as control panels and reagent silos. As a re-
sult, the cost savings for small boilers utilizing shop-assembled
or package FGD systems or processes is not as dramatic as might
be expected and a "break" in FGD system costs for smaller sys-
tems is not observed.
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
28 I I
10,000
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
FIGURE 1
1.0% SULFUR
Barns & McDonnell
LIMESTONE FGD UNIT COSTS
ENGINEERS ARCHITECTS COMBULTANTS
AT 90% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
29 I I
10,000
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
FIGURE 2
1.0% SULFUR
Barns & MCDonnell
LIMESTONE FGD UNIT COSTS
ENGINEERS ARCHITECTS COMBULIANTS
AT 70% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
30 I I
10,000
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
FIGURE 3
1.0% SULFUR
Burns & McDonnell
LIMESTONE FGD UNIT COSTS
ENGINEERS ARCHITECTS COMBULTANTS
AT 50% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
31 I I
10,000
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
FIGURE 4
1.0% SULFUR
Barns & MCDonnell
DUAL ALKALI FGD UNIT COSTS
ENGINEERS ARCHITECTS COMBULIANTE
AT 90% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
32 I I
10,000
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
FIGURE 5
1.0% SULFUR
Burns & MCDonnell
DUAL ALKALI FGD UNIT COSTS
ENGINEERS ARCHITECTS COMBULTANTS
AT 70% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
33 I I
10,000
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
FIGURE 6
1.0% SULFUR
Burns & MCDonnell
DUAL ALKALI FGD UNIT COSTS
ENGINEERS ARCHITECTS CONSULTANTS
AT 50% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
34 I I
10,000
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
FIGURE 7
2.0% SULFUR
1.0% SULFUR
Burns & MCDonnell
SPRAY DRYER FGD UNIT COSTS
ENGINEERS ARCHITECTS CONSULTANTS
AT 90% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
35 I I
10,000
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
FIGURE 8
1.0% SULFUR
Burns & MCDonnell
SPRAY DRYER FGD UNIT COSTS
ARCHITECTS COMMENTS
AT 70% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
36 I I
10,000
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
FIGURE 9
2.0% SULFUR
1.0% SULFUR
Burns & McDonnell
SPRAY DRYER FGD UNIT COSTS
ARCHITECTS COMBULIANTS
AT 50% SO2 REMOVAL
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
3. Radian estimates for 3.54% sulfur
coal.
4. Radian estimates for 0.6% sulfur
coal.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
37 I I
10,000
(3)
(4)
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
2.0% SULFUR
FIGURE 10
1.0% SULFUR
Barns & MCDonnell
DUAL ALKALI FGD UNIT COSTS
ARCHITECTS COMMITANTS
AT 90% SO2 REMOVAL
WITH COMPARISON TO RADIAN
COST ESTIMATES
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
3. Radian estimates for 3.54% sulfur
coal.
4. Radian estimates for 0.6% sulfur
coal.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
38 I I
10,000
(3)
(4)
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
FIGURE 11
2.0% SULFUR
1.0% SULFUR
Burns & McDonnell
DUAL ALKALI FGD UNIT COSTS
ENGINEERS ARCHITECTS COMBULTANTS
AT 50% SO2 REMOVAL
WITH COMPARISON TO RADIAN
COST ESTIMATES
50,000
NOTES: 1. FGD costs include the cost of one spare
absorber module per boiler.
2. The apparent change in the slope of
the curve at 2000 MBtu/hr is due to
40,000
the change in the horizontal scale at
that point.
3. Radian estimate for 0.6% sulfur
coal, without particulate con-
trol device.
FGD COST (1978 $/ MBtu/hr.)
30,000
20,000
39 I I
10,000
(3)
0
0
500
1,000
1,500
2,000
4,000
6,000
8,000
10,000
BOILER SIZE (MBtu/hr.)
3.5% SULFUR
FIGURE 12
2.0% SULFUR
1.0% SULFUR
Barns & McDonnell
SPRAY DRYER FGD UNIT COSTS
ENGINEERS- ARCHITECTS CONSULTANTS
AT 50% SO2 REMOVAL
WITH COMPARISON TO RADIAN
COST ESTIMATES
FG.C.
Memo From
RED CAVANEY
July 21, 1983
Dear Jim:
Attached is a letter which outlines a
potential problem area which might be converted
to the plus column by a timely review on the part
of the Administration. Would be gald to fill you
in on the details.
Hope all is well and best wishes for a good
summer.
Red
Cavancy,
AP
American Paper Institute, Inc.
Red
1619 Massachusetts Avenue, NW, Washington, DC 20036
(202) 332-1050
July 21, 1983
Mr. Edwin L. Harper
Assistant to the President for the
Office of Management and Budget
The White House
Washington, D. C. 20500
Dear Ed:
I am writing to request an appointment with you or one of
your staff in the immediate future to discuss a matter of great
concern--restoration of the quality of our nation's waters--and the
need for reasonable nonpoint source pollution control programs in
order to meet that objective. Nonpoint source pollution involves
runoff from diffuse sources such as urban streets and agricultural
lands.
As you are aware, the Senate Environment and Public Works
Committee is presently considering the addition of a nonpoint source
pollution control amendment to the package of Clean Water Act
amendments reported by the Committee on June 28. We anticipate
Committee action on the nonpoint source issue in early August.
Cavaney, Red
Under the provisions of the 1972 Clean Water Act, a number
of state programs have been developed in order to control nonpoint
sources. Nevertheless, on many water bodies nonpoint source
pollution remains a significant problem. Consequently, public
interest groups are calling for some additional federal and state
emphasis on nonpoint source pollution.
API has been working along with the National Forest Products
Association, American Farm Bureau Federation, National Cattlemen's
Association, Public Lands Council, National Association of
Conservation Districts, Association of State and Interstate Water
Pollution Control Administrators, National Association of Home
Builders, National Grange, National Cotton Council of America, the
American Consulting Engineers Council, and other groups to foster
the adoption of a reasonable provision addressing nonpoint sources
this year. However, we have serious reservations with the proposal
being considered by the Committee. The proposal could substantially
impact farm, forest, ranch and construction activities, as well as
federal, state and local government programs. Moreover, we fear the
amendment, if reported, could result in a controversy that may make
passage of any Clean Water Act amendments impossible this year or
next.
Serving the pulp, paper and paperboard industry
Mr. Edwin L. Harper
July 21, 1983
-2-
However, with the assistance of the Administration, we
believe a reasonable provision can be developed, providing a middle
ground for the diverse factions currently involved in the discussion
of nonpoint sources. To date, the Administration has elected to not
participate in this debate. I understand that the Office of
Management and Budget and the Environmental Protection Agency are in
conflict over the wisdom of Administration participation in the
nonpoint source issue because the former agency objects to the
Committee' any substantial--authorization for the nonpoint
program.
I appreciate the problems involved in additional federal
outlays at this time. However, with a modest level of federal
involvement, a reasonable program can be developed. Operated
primarily at the state and local level, such a program can make
great strides to clean up nonpoint source pollution, and avoid
unproductive and unnecessary regulation.
Further, the measure presently being considered by the
Senate Committee may have major resource implications for other
federal agencies, such as the Corps of Engineers and the Bureau of
Reclamation, which generate some nonpoint problems through their
activities. The implications of this provision may not have been
fully reviewed by the affected agencies. Given this proposal's
possible impacts, the ultimate costs to the Administration upon
enactment may well be far greater than the addition of a modest
nonpoint source program.
The Administration has the opportunity to take a leadership
role in seeking a constructive solution that will be both effective
in reducing nonpoint pollution, and acceptable to farm, ranch and
forest land owners; state and local public officials; and
environmental groups. A small delegation of the above affected
groups would welcome the opportunity to talk with you about this
critical issue.
Sincerely,
Redn
Red Cavaney
Vice President
Government Affairs
RC/MR/lr
American Paper Institute, Inc.
1619 Massachusetts Avenue, NW. Washington. DC 20036
(202) 332-1050
April 12, 1983
The Honorable Faith Ryan Whittlesey
Assistant to the President for
Public Liaison
The White House
Washington, D.C. 20500
Dear Faith:
Thought you Gim- might like the attached copy of our position
paper (for internal use only) regarding the Administration's
natural gas proposal.
We have been very active on the Hill on behalf of the
President and have found contract abrogation and concerns over
total deregulation of "old" gas as the major obstacles. We feel
some hybrid may be able to get out of the Senate Energy Committee.
Best of luck on a good vote.
Warmest regards,
And
Red Cavaney
Vice President
Government Affairs
is
RC/jdp
Attachment
CC: K. Duberstein
J. Cicconi
gan- will hope win on all conversation you give I for t steal work before you
missid MI
norket
maybe tora p loneh long. And
away
Serving the pulp, paper and paperboard Industry
too
PAPER INDUSTRY POSITIONS ON THE
ADMINISTRATION'S NATURAL GAS DECONTROL PROPOSAL
As approved by API's Executive Committee
April, 1983
OVERVIEW:
In keeping with the paper industry's long-standing support of the
free market system, it fully supports the Administration's efforts
to deregulate the wellhead price of all natural gas by a date
certain. While various provisions of the decontrol bill are not
consistent with a free market approach, it is recognized that
these are transitional measures, leading to full decontrol by 1/1/86.
For the long term, the industry particularly endorses the concept
of contract carriage to provide purchaser access to all gas supplies
at competitive market prices.
Major provisions of the Administration's decontrol proposal are:
1) PROVISION:
All new and renegotiated contracts to be deregulated.
POSITION:
The industry supports this provision in keeping with its established
position supporting the free market system.
2) PROVISION:
Unilateral termination of non-renegotiated first sale contracts
during calendar year 1985.
POSITION:
The industry fully supports the sanctity of contracts negotiated
between a willing buyer and a willing seller, and finds it
inappropriate for any government agency to cause these
agreements to be abrogated. However, it is recognized that the
majority of the natural gas contracts were negotiated in an
artificial and controlled environment and do not represent free
market conditions. Therefore, in order to correct those market
distortions caused by regulated conditions, intervention by the
federal government on a one time basis may be necessary to
facilitate the transition to a free market.
3) PROVISION:
Transition price controls - average of new and renegotiated
contracts (gas caps) or NGPA price levels.
POSITION:
The industry supports this provision of the legislation for the
orderly elimination of wellhead price controls on all gas by a
date not later than 1/1/86.
4) PROVISION:
Passthrough restrictions on costs incurred by pipeline companies
including pipeline production affiliates.
POSITION:
Recognizing that the passthrough restrictions are transitional, the
industry fully supports the legislative intent to deregulate the
wellhead price of all gas by 1/1/86. However, it believes that
prudently incurred costs should be passed through in an expeditious
manner during the transition period.
(continued)
5) PROVISION:
Other contract adjustments:
a. Take-or-pay reduction to 70% with associated transportation
obligation;
b. Limits by price caps on indefinite escalator clauses;
C. Area rate provision agreements tied to price caps.
POSITION:
The industry fully supports these interim provisions leading to full
decontrol of the wellhead price of gas not later than 1/1/86.
6) PROVISION:
Removal of access limitations.
POSITION:
The industry strongly supports the provisions which will facilitate
the flow of gas between markets, including the removal of
impediments to interstate movements of gas, and especially
supports the contract carrier authorization.
7) PROVISION:
Repeal of use restrictions.
POSITION:
The industry strongly supports the repeal of the restrictive
industrial and utility Fuel Use Act provisions and Title II of the
NGPA - incremental pricing.
8) PROVISION:
Repeal sections of the NGPA allowing the President or Congress
to reimpose price controls.
POSITION:
The industry strongly supports repeal of this authority.
Coleman
William
O'MELVENY & MYERS
MEDI WILLENE
MARK WOOD
400 SOUTH HOPE STREET
WILLIAM COLEMAN JR."
KENT V. GRAHAM
PHIL WESTBROOK
PERTRAND M. COOPER
LOS ANGELES, CALIFORNIA 90071-2899
CLYDE E. TRITT
RICHARD N. FISHER
1800 M STREET, N. W.
WARREN CHRISTOPHER*
LOWELL C. MARTINDALE. JR.
TELEPHONE (213) 569-6000
EVERETT B CLARY
MICHAEL T. MASIN**
TELEX 67-4122 . 4997795 (ITT)
JAMES E. CROSS
DIANA L. WALKER
WASHINGTON, D. C. 20036-5857
R. BRADBURY CLARK
STUART P. TOBISMAN
BARTON BEEK
JOHN G. NILES
1800 CENTURY PARK EAST
CHARLES G. BAKALY. JR.**
BEN E. BENJAMIN
WILLIAM W, VAUGH
FREDERICK A RICHMAN
TELEPHONE (202) 457-5300
LOS ANGELES, CALIFORNIA 90067-1589
RICHARD E. SHERWOOD
HAROLD M. MESSMER JR.
PHILIP D. IRWIN
FRANCIS J. BURGWEGER, JR.
TELEPHONE (213) 553-6700
DONALD V. PETRONI
JAMES W. COLBERT. 101
TELEX 89-622
TELEX 67-4097
DONN B. MILLER
JAMES V. SELNA
DONALD R. HODGMAN
JOHN F. DAUM
RICHARD 5. VOLPERT
GORDON c. KRISCHER
JOHN H. RONEY
JEFFREY T. PERO
SUITE 1700
DOUGLAS F. RICHARDSON
MARTIN GLENN
610 NEWPORT CENTER DRIVE
JOHN B. BERTERO, JR.
DONALD T. BLISS
HENRY C. THUMANN
EDWARD W. HIERONYMUS
NEWPORT BEACH, CALIFORNIA 92660-6429
LAWRENCE J. SHEEHAN
DAVID E. GORDON
DONALD M. WESSLING
GILBERT T. RAY
TELEPHONE (714) 760-9600 (213) 669-6000
JOHN B. POWER
MICHAEL J. FAIRCLOUGH
RICHARD C. WARMER**
TELEX (714) 720-1397 (DDD) . 4722088 (ITT)
ROBERT J. WHITE
EDWARD J. MCANIFF**
MARK R. STEINBERG
RICHARD C. WHITE
JOSEPH M. MALKIN
SOLOMON M. KAMM
WILLIAM M. WARDLAW
OWEN OLPIN**
July
4 PLACE DE LA CONCORDE
JOHN W. STAMPER
PARIS 8°, FRANCE
WILLIAM D. GOULD
JOHN D. HARDY, JR.
CHARLES W. BENDER
IRA M. FEINBERG
RUSSELL G. ALLEN
28th
TELEPHONE 265 39-33
GIRARD C. BOUDREAU, JR.
DONALD R. SPUEHLER
TELEX 842-660715
GREGORY M. PAUL
GUIDO R. HENRY, JR.
RICHARD R. ROSS
CHARLES F. NIEMETH
ROBERT c. VANDERET
1983
KENDALL R. BISHOP
CHARLES R DIAMOND
RALPH W. OAU
ROBERT E. WILLETT
PATRICK LYNCH
ROBERT A. SIEGEL
DAVID D. WATTS
ULRICH WAGNER
B. BOYD HIGHT**
MATTHEW T. KIRBY
OUR FILE NUMBER
STEPHEN J. STERN
GEORGE M. BARTLETT
JERRY W. CARLTON
CHRISTOPHER C. MURRAY
FREDERICK B. MCLANE
RICHARD G. PARKER**
CHARLES R. MEEKER. ⑉
CARL R. SCHENKER, JR.
JOSEPH RYAN
ARTHUR B. CULVAHOUSE. JR.
MICHAEL W. HARAHAN
MICHAEL NEWMAN
STEPHEN P. PEPE
HOLLY E. KENDIG
WILLIAM G. ADAMS
SCOTT H. DUNHAM
LAURENCE G. PREBLE
RALPH J. SHAPIRA
A. ROBERT PISANO
CHARLES c. READ
WRITER'S DIRECT TELEPHONE
ROBERT S. DRAPER
OF COUNSEL
JOHN F. AISO
PERRY A. LERNER
(202) 457-5325
MITCH MORIYASU MICHINO
I
MEMBER D. c. BAR
"MEMBER CALIF. AND D.C. BARS
OTHERS ADMITTED IN CALIF. NOT D.C.
Honorable James W. Cicconi
Special Assistant to the President
and to the Chief of Staff
The White House
Washington, D.C.
Dear Jim:
As you know, I serve as Chairman of the Board of
the NAACP Legal Defense and Educational Fund, Inc. ("LDF").
As a result of a lawsuit filed by LDF in 1980, NAACP Legal
Defense and Educational Fund, Inc. V. Campbell, 504 F. Supp.
1365 (D.D.C. 1981), which resulted in a ruling by Judge
Gesell favorable to us, the Legal Defense Fund has partici-
pated in the Combined Federal Campaign for the last two years.
Judge Gesell ruled that the requirement that CFC participants
provide "direct services to persons in the fields of health
and welfare services" was invalidated in 1981 as "too vague
to comport with the strict standards of specificity" required
by the First Amendment. LDF V. Campbell, 504 F.Supp. at 1366-67.
On January 10, 1983, President Reagan issued
Executive Order No. 12404 in an effort to reinstate the
direct services requirement but with greater specificity.
The announced purpose of the new Executive Order was to
exclude legal defense funds from the CFC. Devine memorandum
of Feb. 2, 1982, "New Executive Order for the Combined Federal
Campaign."
Honorable James W. Cicconi
Page Two
On July 15, 1983, however, Judge Joyce Green ruled
that Executive Order 12404 violated the First Amendment.
NAACP Legal Defense and Educational Fund, Inc. V. Devine,
No. 83-0928 (D.D.C.). Judge Green ruled that the CFC con-
stitutes a limited public forum and that the government can-
not exclude some charitable organizations because their
message is controversial.
The issue that must now be resolved is what rules
will govern the 1983-84 campaign. It is important that this
question be resolved expeditiously because preparations for
the 1983 Campaign are already well under way.
Although legal defense funds must be allowed to
participate in the 1983-84 Campaign as the result of Judge
Green's order, the Office of Personnel Management has not
yet begun to implement the Court's decision. Rather,
Director Devine has announced that he plans to appeal the
Court's ruling but he has not yet done so. In the meantime,
Local Federal Coordinating Committees still are operating
under instructions from OPM to make eligibility decisions
on the basis of Executive Order 12404, even though Judge
Green has declared it invalid. Furthermore, while Director
Devine has announced that the start of the Campaign will be
delayed until mid-October, in order to permit orderly reso-
lution of the claims of legal defense funds, we were informed
last week by one Local Committee that its Campaign will
begin on September 13, and that the NAACP Legal Defense Fund
will be excluded on the basis of the Executive Order. When
informed of Judge Green's decision, the Local's reply was
that OPM had not changed its instructions.
This type of confusion will severly damage the
1983-84 Campaign. The only fair action at this time is for
OPM to announce immediately that the 1983 Campaign will be
conducted under the pre-existing regulations. The government
has the right to appeal Judge Green's decision, although I do
not believe such an appeal should be taken. However, in the
event an appeal is taken, it should be directed toward future
Campaigns and should not be used to further delay and confuse
the current Campaign.
Specifically, I urge that should an appeal be taken,
the government not seek a stay of Judge Green's ruling. In
addition to the confusion that would result, such a stay
would be incquitable. It was the Office of Personnel Manage-
ment that delayed resolution of the lawsuit until the eve of
Honorable James W. Cicconi
Page Three
the Campaign, by delaying issuance of regulations under
Executive Order 12404. Moreover, our participation in the
1983-84 Campaign will not harm the CFC. Legal defense funds
have participated in the past two years, and in each year
contributions increased significantly. It seems to me the
only fair and just thing is to announce that the 1983-84
Campaign will be conducted under the same rules as applied
in the 1982-83 Campaign. As you know, the Majority Leader
of the Senate has sent a letter to Ed Meese making the same
request.
Please call me and I will be happy to discuss this
matter further.
With kindest regards,
Sincerely,
William T. Coleman, Jr.
ID # 159621 CA
NE that reg handleti ready
OFFICE OF CABINET AFFAIRS
ACTION TRACKING WORKSHEET
Action resulting from:
Document Date: 83,08,01
document (attached)
telephone call
From:
tim Cicconi
meeting (attach conference report
if available)
Date Received: 83/08/02
Subject:
Sends Fuller letter to Cicconi from
William T. Coleman Jr. re: new regulations
governing C FC for stoffing + distribution
ACTION CODES:
A- Appropriate Action
D - Draft Response
Direct Reply w/Copy
B - Briefing Paper
F
- Furnish Fact Sheet
S- For Signature
C - Comment/Recommendation
I- Info Copy Only/No Action Necessary
X - Interim Reply
ROUTE TO:
Date Sent
Name
Action Codes
Date Due
Action Taken
DD/
83/08/04
1. Clarey
A
/ /
ToJoeMorris via H.P.Goldfict
83,08,11
2. FULLER
A
for response
/ /
letter attached
83,08/11
3 Cicconi
A
/ /
/ /
No need 10 to
/ /
/ /
respond
/ /
/ /
/ /
COMMENTS: OPM put toyether a long letter but
H.P. QI Jelt that the W.H. shouldcurrid direct
moolvement so a Short response is attached
3
Response attached
Originator:
Dunlop
Faoro
Fuller
Gonzalez
Hart
Hodapp
KEEP THIS WORKSHEET ATTACHED TO THE ORIGINAL INCOMING MATERIAL AND
WHEN THE ASSIGNED ACTION IS COMPLETE,
RETURN TO:
Office of Cabinet Affairs
Attention:
Karen Hart (x-2823)
West Wing/Ground Floor
THE WHITE HOUSE
WASHINGTON
159621
August 1, 1983
MEMORANDUM FOR CRAIG FULLER
FROM:
Jim Cicconi,
SUBJECT:
Letter from Bill Coleman
Attached is a letter from Bill Coleman, who is writing about
the proposed new regulations governing the Combined Federal
Campaign. He is writing in his capacity as chairman of
the NAACP Legal Defense and Educational Fund.
It is forwarded for staffing and for distribution as you
feel appropriate.
Thanks.
CC: Joe Wright
THE WHITE HOUSE
WASHINGTON
August 11, 1983
Dear Bill:
Thank you for your letter of July 28, 1983 regarding the
Combined Federal Campaign. I recognize and appreciate your
special interest in the rules governing the CFC. While I
was very concerned about the issues raised in your letter,
given the fact that such issues are currently in litigation,
it would be inappropriate for the White House to become
involved.
I would, however, suggest that you contact Joseph A. Morris,
General Counsel of the Office of Personnel Management, in
order that they be fully apprised of all relevant informa-
tion as appropriate.
With best wishes,
Sincerely,
James W. Cicconi
Special Assistant
to the President
Mr. William T. Coleman, Jr., Esq.
O'Melveny & Meyers
1800 M Street, NW
Washington, D.C.
20036-5857
CC: Joseph A. Morris
Column
U.S
JAMES C. GREENE
MARK WOOD
O'MELVENY & MYERS
400 SOUTH HOPE STREET
WILLIAM T. COLEMAN, JR."
KENT V. GRAHAM
PHILIP F. WESTBROOK
BERTRAND M. COOPER
LOS ANGELES, CALIFORNIA 90071-2899
CLYDE E. TRITT
RICHARD N. FISHER
1800 M STREET, N. W.
WARREN CHRISTOPHER**
LOWELL c. MARTINDALE, JR.
TELEPHONE (213) 669-6000
EVERETT B. CLARY
MICHAEL T. MASIN**
TELEX 67-4122 4997795 (ITT)
JAMES E. CROSS
DIANA L. WALKER
WASHINGTON, D. C. 20036-5857
R. BRADBURY CLARK
STUART P. TOBISMAN
BARTON BEEK
JOHN G. NILES
CHARLES G. BAKALY, JR.**
BEN E. BENJAMIN**
1800 CENTURY PARK EAST
WILLIAM W. VAUGHN
FREDERICK A. RICHMAN
TELEPHONE (202) 457-5300
LOS ANGELES, CALIFORNIA 90067-1589
RICHARD E. SHERWODD
HAROLD M. MESSMER, JR.
PHILIP D. IRWIN
FRANCIS J. BURGWEGER, JR.
TELEPHONE (213) 553-6700
DONALD V. PETRONI
JAMES W. COLBERT, III
TELEX 89-622
DONN B. MILLER
JAMES V. SELNA
TELEX 67-4097
DONALD R. HODGMAN
JDHN F. DAUM
RICHARD S. VOLPERT
GORDON E. KRISCHER
JOHN H. RONEY
JEFFREY T. PERD
SUITE 1700
DOUGLAS F. RICHARDSON
MARTIN GLENN
JOHN B. BERTERO, JR.
DONALD T. BLISS*
HENRY C. THUMANN
EDWARD W. HIERONYMUS
May
610 NEWPORT CENTER DRIVE
NEWPORT BEACH, CALIFORNIA 92660-6429
LAWRENCE J. SHEEHAN
DAVID E. GORDON
DONALD M. WESSLING
GILBERT T. RAY
9th
TELEPHONE (714) 760-9600 (213) 669-6000
JOHN B. POWER
MICHAEL J. FAIRCLOUGH
RICHARD C. WARMER**
ROBERT J. WHITE
TELEX (714) 720-1397 (DDD) . 4722088 (ITT)
EDWARD J. MCANIFF**
MARK R. STEINBERG
RICHARD C. WHITE
1983
JOSEPH M. MALKIN
SOLOMON M. KAMM
WILLIAM M. WARDLAW
4 PLACE DE LA CONCORDE
OWEN OLPIN**
JOHN W. STAMPER
WILLIAM D. GOULD
JOHN D. HARDY, JR.
PARIS 8°, FRANCE
CHARLES W. BENDER
IRA M. FEINBERG
TELEPHONE 265 39-33
GIRARD E. BOUDREAU, JR.
RUSSELL G. ALLEN
DDNALD R. SPUEHLER
GREGORY M. PAUL
TELEX 842-660715
GUIDO R. HENRY, JR.
RICHARD R. ROSS
CHARLES F. NIEMETH
ROBERT c. VANDERET
KENDALL R. BISHOP
CHARLES P. DIAMOND
RALPH W. DAU
ROBERT E. WILLETT
PATRICK LYNCH
ROBERT A. SIEGEL
DAVID D. WATTS
ULRICH WAGNER
B. BOYD HIGHT**
MATTHEW T. KIRBY
STEPHEN J. STERN
GEORGE M. BARTLETT
OUR FILE NUMBER
JERRY W. CARLTON
CHRISTOPHER C. MURRAY
FREDERICK B. MCLANE
RICHARD G. PARKER
CHARLES R. MEEKER, ⑉
CARL R. SCHENKER, JR.**
JOSEPH RYAN
ARTHUR B. CULVAHOUSE, JR.**
750,110-59
MICHAEL W. HARAHAN
MICHAEL NEWMAN
STEPHEN P. PEPE
HOLLY E. KENDIG
WILLIAM G. ADAMS
SCOTT H. DUNHAM
LAURENCE G. PREBLE
RALPH J. SHAPIRA
A. ROBERT PISANO
CHARLES C. READ
WRITER'S DIRECT TELEPHONE
ROBERT S. DRAPER
OF COUNSEL
202/457-5325
JOHN F. AISO
PERRY A. LERNER
MITCH MORIYASU MICHINO
MEMBER D. c. BAR
"MEMBER CALIF. AND D. C. BARS
OTHERS ADMITTED IN CALIF. NOT D.C.
Mr. James W. Cicconi
Special Assistant to the President
and Special Assistant to the Chief of Staff
The White House
Washington, D.C. 20500
Re
Further Consideration of the Status of Kuwait
Under the Mineral Lands Leasing Act of 1920
Dear Jim:
We spoke earlier this year concerning the then-
pending reconsideration by the Department of the Interior of
the December 1982 decision that Kuwait is a qualified country
under the Mineral Lands Leasing Act of 1920 (MLLA), which
would affect our client Santa Fe International Corporation.
As you know, on March 10, 1983, Secretary Watt determined
that Kuwait is disqualified under the MLLA on the ground
that Kuwait discriminated against American companies during
the 1970's as it reduced or eliminated private ownership in
the oil sector. We believe that this decision was based on
incomplete and erroneous information about Kuwait's prac-
tices, largely as a result of the fact that the Interior
Department did not provide Santa Fe or its shareholder, Kuwait
Petroleum Corporation, an opportunity to comment on this
discrimination issue.
I have enclosed a copy of a letter to Secretary
Watt and accompanying materials delivered on May 4, 1983.
The enclosed memorandum demonstrates that companies with
American ownership long enjoyed a paramount position in the
oil industry in Kuwait and that Kuwait did not discriminate
in any way against American interests as it increased
governmental control over the oil industry. We believe that
#2 - Mr. James W. Cicconi - 5/9/83
this information should compel the Secretary to consider
this matter further and to confirm the qualified status of
Kuwait under the MLLA. Qualification of Kuwait would be
consistent with long-standing interpretations of the MLLA,
with the fundamental American policy favoring the attraction
of foreign investment, with the pressing need for capital
formation to permit frontier oil and gas exploration, and
with good diplomatic relations with Kuwait and other countries
which have found it necessary to choose state ownership in
the oil sector.
We have requested a meeting with Secretary Watt on
this matter on May 18. We would appreciate your supporting
further consideration through the Senior Inter-Departmental
Group on International Economic Policy or other appropriate
avenues now that more complete and accurate information is
available. I have also written to Danny Boggs in this
connection.
Thank you for your attention to this matter. We
would be happy to respond to any questions or to provide any
additional information.
Very truly yours,
William T. Coleman, Jr.
of O'MELVENY & MYERS
Enclosures
Foreign Agents Registration Act
No. 3346
THE WHITE HOUSE
WASHINGTON
May 16, 1983
MEMORANDUM FOR JIM CICCONI
FROM:
DANNY BOGGS
SUBJECT:
Status of Kuwait Under the MLLA of 1920
I spoke to Coleman and his associates sometime earlier in the
year, between the suspension of the original decision and the
March 10 determination of disqualification. I have not done any
kind of definitive legal study on this, but I would put some
credence in the argument that a strict application of the Kuwait
decision to all similar situations might reduce the number of
companies or countries able to lease federal land to a very small
number.
THE WHITE HOUSE
WASHINGTON
May 10, 1983
TO: DANNY BOGGS
Please see the attached letter
from Bill Coleman.
What do you think of his
argument? (I have not yet
responded to him.)
Thanks.
Jim Cicconi
for
THE WHITE HOUSE
WASHINGTON
was coord d
w/ State, SIG-EP EP
and NSC
"watt made clear his
intentions : shulty
said to do what
you have to
Columan Bill
(suc also Schenker, Carl)
O'MELVENY & MYERS
JAMES C. GREENE
WILLIAM G. ADAMS
400 SOUTH HOPE STREET
WILLIAM T. COLEMAN, JR.
LAURENCE G. PREBLE
PHILIP F. WESTBROOK
A. ROBERT PISANO
LOS ANGELES, CALIFORNIA 90071-2899
CLYDE E. TRITT
ROBERT S. DRAPER
1800 M STREET, N.W.
WARREN CHRISTOPHER**
MARK WOOD
TELEPHONE (213) 669-6000
EVERETT B. CLARY
KENT V. GRAHAM
JAMES E. CROSS
BERTRAND M. COOPER
WASHINGTON, D. C. 20036-5857
TELEX 67-4122
HUGH L. MACNEIL
RICHARD N. FISHER
R. BRADBURY CLARK
LOWELL c. MARTINDALE, JR.
BARTON BEEK
MICHAEL T. MASIN**
1800 CENTURY PARK EAST
CHARLES G. BAKALY, JR.
DIANA L. WALKER
TELEPHONE (202) 457-5300
LOS ANGELES. CALIFORNIA 90067-1589
WILLIAM W. VAUGHN
STUART P. TOBISMAN
RICHARD E. SHERWOOD
JOHN G NILES
TELEPHONE (213) 553-6700
PHILIP D. IRWIN
BEN E. BENJAMIN
TELEX 89-622
DONALD V. PETRONI
FREDERICK A. RICHMAN
TELEX 67-4097
DONN B. MILLER
HAROLD M. MESSMER, JR.
DONALD R. HODGMAN
FRANCIS J. BURGWEGER, JR.
RICHARD S. VOLPERT
JAMES W. COLBERT, III
SUITE 1700
JOHN H. RONEY**
JAMES V. SELNA
DOUGLAS P. RICHARDSON
JOHN F. DAUM
610 NEWPORT CENTER DRIVE
JOHN B. BERTERO, JR.
GORDON E. KRISCHER
NEWPORT BEACH, CALIFORNIA 92660-6429
HENRY C. THUMANN
JEFFREY T. PERO
LAWRENCE J. SHEEHAN
MARTIN GLENN
TELEPHONE (714) 760-9600 (213) 669-6000
DONALD M. WESSLING
DONALD T. BLISS*
TELEX (714) 720-1397 (DDD) 742-2088 (ITT)
JOHN B. POWER
EDWARD W. HIERONYMUS
RICHARD C. WARMER**
DAVID E. GORDON
EDWARD J. MCANIFF**
GILBERT T. RAY
March
RICHARD c. WHITE
MICHAEL J. FAIRCLOUGH
4 PLACE DE LA CONCORDE
SOLOMON M. KAMM
ROBERT J. WHITE
STANTON H. ZARROW
MARK R. STEINBERG
9th
PARIS 8°, FRANCE
OWEN OLPIN**
JOSEPH M. MALKIN
TELEPHONE 265 39-33
WILLIAM D. GOULD
WILLIAM M. WARDLAW
CHARLES W. BENDER
JOHN W. STAMPER
1983
TELEX 842-680715
GIRARD E. BOUDREAU, JR.
JOHN D. HARDY, JR.
DONALD R. SPUEHLER
IRA M FEINBERG
GUIDO R. HENRY, JR.
RUSSELL G. ALLEN
CHARLES F. NIEMETH
GREGORY M. PAUL
KENDALL R. BISHOP
RICHARD R. ROSS
RALPH W. DAU
ROBERT C. VANDERET
PATRICK LYNCH
CHARLES P. DIAMOND
DAVID D. WATTS
ROBERT E. WILLETT
OUR FILE NUMBER
B. BOYD HIGHT**
ROBERT A. SIEGEL
STEPHEN J. STERN
ULRICH WAGNER
JERRY W. CARLTON
MATTHEW T. KIRBY
FREDERICK B. MCLANE
GEORGE M. BARTLETT
CHARLES R. MEEKER, III
CHRISTOPHER C. MURRAY
JOSEPH RYAN
RICHARD G. PARKER
750,110-59
MICHAEL W. HARAHAN
CARL R. SCHENKER, JR.
STEPHEN P. PEPE
ARTHUR B. CULVAHOUSE, JR.
WRITER'S DIRECT TELEPHONE
OF COUNSEL
JOHN F. AISO
PERRY A. LERNER
MITCH MORIYASU MICHINO
(202) 457-5325
-
"MEMBER D. c. BAR
"MEMBER CALIF. AND D. C. BARS
OTHERS ADMITTED IN CALIR NOT D. c.
Mr. James W. Cicconi
Special Assistant to the President
and to the Chief of Staff
The White House
Washington, D.C. 20500
Dear Jim:
I am enclosing herewith the note which the
Kuwait Ambassador has given to the State Department.
After reading it, you can understand why I have been
trying to get some attention paid to the foreign policy
aspect of any decision which Secretary Watt might make.
With kindest regards,
Sincerely,
Biu
William T. Coleman, Jr.
of O'MELVENY & MYERS
Enclosure
Translation of Diplomatic Note From the
Minister of Foreign Affairs of the State of Kuwait
to the Secretary of State of the United States of America
(Delivered March 4, 1983)
I wish you the best of times. I am pleased to
express our pleasure for the good relations existing between
our two countries and that we hope it will increase and de-
velop. I would like to refer to the American decision con-
cerning the utilization of the federal American lands that has
a negative impact on the Kuwaiti interests in the United
States.
As you are aware, my government has for some years
been concerned about its status as a "reciprocal nation" under
the Mineral Lands Leasing Act. My government has pursued this
question because of Kuwait's practical interest in doing
business in the energy industries of the United States.
Kuwait has long viewed the United States as an area
of singular commercial opportunity. The United States is the
largest single industrial economy in the world and it exempli-
fies, par excellence, that commercial and entrepreneurial ethos
which also characterizes, we believe, Kuwait's own partici-
pations in local and in international trade.
As you know, this lively Kuwaiti interest in U.S.
business opportunites is shared also by the Kuwait Petroleum
Corporation (KPC), and it led to the successful bid by KPC in
October 1981 for all of the shares of Santa Fe International
Corpration (SFIC). My government was gratified by the positive
view of that acquisition which was taken by the U.S. adminis-
tration, notably under the formal review processes supervised
by the Committee on Foreign Investment in the United States
(CFIUS). We believe that the explanations given by KPC (nota-
bly the well-publicized views of KPC's Chairman, Sh. Ali
Khalifa Al-Sabah; also the testimony to a Congressional
Committee by KPC's Deputy Chairman, Mr. Abdul Razak Hussain)
convinced the various U.S. authorities of KPC's bona fides --
particularly the non-political and commercial policies which it
would observe. KPC has lived up to its stated intentions
regarding the future of Santa Fe under Kuwaiti ownership and
has more than doubled SFIC's capital investments in the year
following the acquisition.
Detailed legal comments in support of my government's
application for recognition of its reciprocal status have been
made by our U.S. legal advisors and by the lawyers of SFIC. It
would be superfluous to refer here to this extensive docu-
mentation.
I have to inform you that my government is seriously
disappointed over the handling by the Interior Department of
Kuwait's application for recognition of its reciprocal status
under the Mineral Lands Leasing Act of 1920 (MLLA). Our formal
request for recognition dates from about two and a half years
ago. We fully understood the necessity to wait our turn in a
review process which involved other countries and we have taken
care to respond as fully as possible to the queries raised by
the responsible Department. It nevertheless remains a fact
that the review process has taken an extraordinarily long time
to come to a conclusion.
Given the nature of Kuwait's case, and the parallels
which it offers with access by the public to some State-owned
natural resources in say, the U.K., Mexico and Venezuela, it
came as a relief to my goverment (but as no surprise) that the
Interior Department eventually found in favour of Kuwait in its
decision dated 29 December 1982. In that decision, Kuwait was
declared a reciprocal nation under the MLLA by the Assistant
Secretary of the Department of the Interior. The Kuwaiti
government assumed, naturally enough, that thorough administra-
tive procedures had eventually revealed that this finding was
wholly consistent with the requirements of the MLLA and with
the precedent decisions made by the Department of the Interior.
You can doubtless comprehend my government's surprise when the
Interior Department within one month actually revised its
finding and delayed its final decision on Kuwait's reciprocal
status.
My government and its legal advisors in the United
States are both at a loss to comprehend the factual basis for
the hold-up in the Department's ruling. The Kuwaiti government
is concerned that unknown issues, not related to the technical
and legal determination required by the MLLA, have come into
play. Naturally, we were glad to learn from the evidence given
by Secretary Watt on 2 February 1983 to the Senate Energy and
Natural Resources Committee, that a final determination will be
given "within the next 30/40 days". My government is neverthe-
less most anxious to have the opportunity to know fully the
grounds on which this administrative delay has occurred. My
government is also very concerned that it be given the opportu-
nity to comment on these grounds and to fully discuss any addi-
tional points which may be raised by the Interior Department
pertaining to Kuwait's application for recognition of recipro-
cal status. It goes without saying that my government wishes
-2-
to provide its views to the Department of the Interior prior to
the issuing of the "final determination".
My government believes that this hesitancy at the
Interior Department has been an unfortunate development which
harms legitimate Kuwaiti business interests in the United
States. My government looks to full consultation with the
appropriate U.S. authorities concerning this unexpected
development and is confident that the facts of the matter will
lead to a speedy confirmation of the earlier decision.
Therefore, I would like you to take this subject into
your direct consideration hoping that you will reach the posi-
tive steps that contribute in fostering and strengthening the
relations between our two countries.
Yours sincerely,
s/Shaikh Sabah A. J. Al-Sabah
Deputy Prime Minister, Minister
of Foreign Affairs and Minister
of Information
-3-
WINSTEAD, MCGUIRE,
W. MIKE BAGGETT
ALAN J. HARLAN
MICHAEL J. QUILLING
STANLEY K BARTH
CLIFFORD D. HARMON
DARREL A. RICE
WILLIAM E. BARTHOLDT, JR.
STEVEN A. HARR
PHILIP B. RICHTER
SECHREST & MINICK
EARL T. BERRY
DONALD F. HAWBAKER
RANDALL E. ROBERTS
JOHN R. BONICA
THOMAS R. HELFAND
JOHN C. UTHERFORD
NAN B BRALEY
RONALD L. HOLMES
THOMAS G. SCHROETER
A PROFESSIONAL CORPORATION
PAUL D. BUDD
THOMAS W. HUGHES
WILLIAM B. SECHREST
JAMES R. CALLAHAN
JEFF JOYCE
PAUL F. SEILER
ATTORNEYS AND COUNSELORS
WM. KEVIN CHERRY
ALLEN W. KIMBROUGH
ARTHUR F. SELANDER
ROBERT E. CRAWFORD. JR.
BARRY R. KNIGHT
KAY SHELTON
R.M. CROWE, JR.
J. KENNETH KOPF
DANIEL C. STEWART
1700 MERCANTILE DALLAS BUILDING
WILLIAM L. DECKELMAN. JR.
RICHARD O KOPF
PHILIP W. STEWART
DANIEL A. DECKER
JAMES J. LEE
GARY STOLBACH
DALLAS, TEXAS 75201
JOHN N. DINAN
JAY J. MADRID
KEVIN A. SULLIVAN
DAVID W ELMOUIST
T. RANDALL MATTHEWS
NANCY A, THOMAS
J. ROBERT FISHER
CHARLES J. MCGUIRE
J. MAXWELL TUCKER
214/742-1700
JEFFREY A. FORD
W. TED MINICK
CHRISTOPHER R. TURNER
WILLIAM A.FRENCH 111
RUSSELL L. MUNSCH
JOHN M WALKER. JR
TELEX: 73-0051
ROBERT H. FROST
THOMAS W. MYERS
J. RICHARD WHITE
THOMAS E. GILLESPIE
ROBERT A. NELSON
STEPHEN P. WILKES*
TELECOPIER: 214/698-8390
JAMES W. GOGGANS
STEVEN D NELSON
CHERRY D. WILLIAMS
ROBERT H. GRABNER, JR.
JOHN M. NOLAN
PETER WINSTEAD
J. DAVID GRIFFIN
THOMAS W. OLIVER
DONALD L. WOODSMALL
JEFFREY A. HAGE
MICHAEL L. PARHAM
JAMES G. WORLEY
DIRECT DIAL:
RICHARD G. HAMON
DALE PLAXCO
LYNDA ZIMMERMAN
JOE HARDT
JOHN PRICE
OF COUNSEL
"ADMITTED IN STATE OTHER THAN TEXAS
DAVID A DEAN
December 22, 1983
Mr. Jim Cicconi
Special Assistant to the President
White House
1st Floor, West Wing
Washington, D.C. 20500
Dear Jim:
In a few days you will receive a special request for support from an organization
that is very important to me personally: The Dean Learning Center.
There are literally millions of Americans with some form of language learning
difficulty. The Dean Learning Center is addressing this special problem with
a total program including an evaluation-diagnostic division serving both adults
and children, a complete school from pre-primary through eighth grade, and
a teacher training division that has served as the model for many others. Its
faculty includes many of the most highly trained and skilled teachers, practi-
tioners, and lecturers in the learning disability area. They are dedicated to ser-
ving others and are enthusiastic about the Center, its past accomplishments
and future potential. We feel that the Center is literally on the cutting edge
of research and advancements in this important area. It effects so many.
Among the numerous organizations that appeal for contributions, Dean is es-
pecially deserving. I hope you will give serious consideration to the Center's
need for support and that you will join me in making a generous, tax-deductible
donation.
May the holiday season be a joyous time for you and your family, and I wish
you a healthy and prosperous New Year.
Sincerely,
claid
David A. Dean
DD;cb