OCR Page 1 of 4August 3, 1951
white House
EXECUTIVE MANSION RENOVATION
PROGRESS REPORT TO AND INCLUDING AUGUST 2, 1951
To the Chairman and Members of the Commission:
WORK 100% COMPLETE
TROMAN
DEMOLITION
FOOTINGS
GUNITE
DISMANTLING
SHORING
UNDERPINNING
EXCAVATION
STRUCTURAL STEEL
SUB-DRAINAGE
CONCRETE - 99%
Remaining work - Complete floor fills and floor slab of Exhaust Tunnel.
BRICK & TILE - 99%
Remaining work - Miscellaneous partitions and fireplaces.
MISCELLANEOUS IRON - 85%
Item complete except for installation of miscellaneous pipe rails and ladders.
ORNAMENTAL METAL - Reconditioning old materials.
LATH & PLASTER - 98%
Lathing - Complete. Plastering - All flat work complete except in misc. locations.
Ornamental work in Main Lobby and Hall proceeding and practically complete.
INSULATION - 90% - No Change
INTERIOR MARBLE - 40% - No Change
Main Lobby pilasters and misc. marble received. Marble work on Ground Floor is
complete except floor in Old Kitchen and mantels.
EXTERIOR STONE - 25% - No Change
Stone work on roof about complete. Shop drawings being submitted.
HOLLOW METAL - 25% - No Change (Strike continues at Dahlstrom Plant)
ROOF & SHEET METAL - 20% - No Change
Entire roof now water-tight. Laying quarry tile on Promenade.
WATERPROOFING - 95% - No Change
UNDERGROUND VAULTS - 98% - Completing backfill.
APPROACH WORK - 5% - Driveway slab on N.W. side installed.
STRUCTURAL GLASS - 10% - Dental Room and three (3) Showers tiled.
CARPENTRY - 95% - No Change other than misc. grounds.