# 457
January 11, 1946
The following outline of plans for construction work on the
White House grounds is for the information of correspondents:
The $1,650,000 construction projects at the white House, may
be divided into four main units:
(1) Addition to the Executive offices.
(2) Completion of the recently constructed East Wing.
(3) Interior alterations to the Mansion.
(4) Landscaping and improvements to the Grounds.
NARA
1.
The first construction work will be the addition to the
Executive Offices - the West Wing.
This new addition will extend south of the Executive office
along West Executive Avenue and will be similar in construction and
detail to the existing building. The new West facade will be symmetrical
with a new main entrance in the center.
There will be fifteen thousand feet of new office space to
accomodate the President's Executive Assistants, together with a large
clerical force, now in office quarters outside the White House. An
auditorium will be constructed to the south of the President's Office
with seating arrangements for three hundred and seventy-five (375)
persons. This will provide urgently needed facilities for ceremonies,
Press Conferences, Radio Broadcasts, Photography, Television, Motion
Pictures and for other purposes such as meetings and social entertain-
ments that have been held in the formal East Room of the Mansion.
There will be facilities also in the new addition for increased
filing room space, a larger mail room, a small cafeteria, a mimeograph
room, and necessary storage and utility rooms.
2.
When the West addition is finished the personnel now occupying
offices in the East Wing will be transferred to the new quarters and
construction will begin on the completion of the East Wing for its
originally intended purpose as a White House Museum. Plans for the
East Wing were under way the day after war was declared and the corner-
stone was laid by the late President Roosevelt on November 5, 1942.
During the war, emergency offices in this wing were used by Admiral
William D. Leahy, Harry L. Hopkins, Secretary Vinson, Secretary Byrnes,
John W. Snyder, and other Presidential Aides.
The late President was most interested in the development
of plans for this wing and Lorenzo S. Winslow, Architect of the White
House, had made numerous sketches for a new East Entrance and Museum
at intervals since 1935. The new East Wing will facilitate the
reception of guests at large White House social functions, and its
use as a museum will tend to further the privacy and homelike atmosphere
of "The President's House", as the Executive Mansion was called in the
early days of its occupancy. Historic furniture, chinaware, papers
and other articles used by the various Presidential families were on
display on the ground floor of the White House before the war and the
Museum will contain various rooms that will permit these articles to
be shown according to the historical and political periods of the
country's history to which they belonged.
The East Wing now contains also the quarters of the White
House guards, the wartime bomb shelter and various store rooms and
offices.
3. All alterations to the Mansion itself will be within the
building. The architect, Mr. Winslow, emphasizes that no exterior
changes will mar the historic appearance of the White House. These
interior alterations include complete modernization of the heating
system, which utilizes hot air, hot water, and high and low pressure
steam, and has been in use since 1902.